(4 years, 5 months ago)
Commons ChamberOn current plans, decant would be in the mid-2020s and the proposed approach to the works and the schedule would be put to both Houses for agreement before that. While the restoration work continues to be vital, we are currently reviewing the approach, and we of course welcome the views of the hon. Gentleman and all colleagues.
Is it not the case that these plans have now effectively been mothballed and scrapped, and that Parliament is not going to proceed with the full refurbishment as originally planned? If that is the case, what measures will be put in place to maintain this wonderful historic building and keep it safe from fire and damage?
The hon. Gentleman is quite right about the risks from fire, flood and falling masonry. He was of course a distinguished member of the Joint Committee on the Palace of Westminster, and those works remain vital. We all have in mind the need for the uninterrupted effectiveness of Parliament in scrutinising the Government and in working on behalf of our constituents, but we also know that we must do that while providing the good value for money that is rightly demanded by our constituents, and that is what is at the heart of the current review.