Midland Main Line (Electrification) Debate
Full Debate: Read Full DebateClive Betts
Main Page: Clive Betts (Labour - Sheffield South East)Department Debates - View all Clive Betts's debates with the Department for Transport
(9 years, 1 month ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
I beg to move,
That this House has considered electrification of the Midland Main Line.
There is no doubting the critical need for the country to keep its rail network up to date. Over the past 20 years, passenger numbers have doubled. Between 1997 and 2010, the number of inter-city trains went up from 580 per day to 1,228 per day. Current growth in use stands at 4%, and total movement of freight by rail is rising by 2.5% per year. With demand growing as it is, it is entirely understandable that there is cross-party consensus on the need for bold and ambitious upgrade works.
On the midland main line specifically, Leicester, Nottingham and Derby are all experiencing passenger growth at rates above the national average, and demand for rail in the east midlands as a whole is expected to rise by 16% by 2019. Coupled with that is the chronic lack of investment in the line over the past two decades when compared with other routes.
From anyone’s perspective, electrification is the next logical step for the rail network. Compared with a traditional service, an electrified line is more cost efficient, greener, thanks to reduced carbon emissions, and served by better rolling stock. There are also benefits in terms of reliability, connectivity, capacity and economic growth.
To take the midland main line as a specific example, electrifying the line from Bedford to Sheffield could cut carbon emissions by 13,000 tonnes per year. The project would also provide the higher W10 gauge clearance along the whole route, making it more accessible for freight, so there would be a further indirect environmental benefit, as the growing demand for freight could be met, taking more lorries off the roads. To give a rough idea of that benefit, on a traditional service a gallon of diesel will carry 1 tonne of freight 246 miles by rail as opposed to 88 miles by road; on an electrified line, of course, the environmental benefits would be even greater.
As for the economic benefits, it has been estimated that by cutting the costs of rolling stock, energy, track access and maintenance, electrification will cut rail industry costs by over £60 million per year, reducing the cost of the railway to the taxpayer. The midland main line serves one of the fastest growing areas of England, and a report prepared for east midlands councils and the South Yorkshire Passenger Transport Executive by the consultancy firm Arup estimated that electrification would generate £450 million-worth of wider economic benefits. If the Government want to get serious about growing our economic potential outside the south-east and giving the northern powerhouse brand some substance, as a starting point they will have to commit to funding the midland main line project, as well as the TransPennine route upgrade.
Lack of investment in infrastructure has been one of the key restraints on growth outside London. In 2013-14 expenditure per head on transport capital was £166 in the north, whereas in London it was £332. Treasury figures published earlier in the year show that planned infrastructure expenditure on transport in real terms from 2015-16 is £2,604 per head in London, but only £391 per head in Yorkshire and the Humber, and just £346 per head in the east midlands. The lack of transport investment means that cities and towns in the north cannot link up into a single economy. Instead, we are still operating as single units and are not able to build up the economic scale and weight that would allow us to play to our strengths and complete globally.
The midland main line might feature only as a footnote in most discussions of the northern powerhouse, if it features at all—and I certainly do not want to get into a debate about what counts as “the north”, which might keep us all here a lot longer than we would like—but it is a vital link in the chain that will help with the Government’s stated objective of rebalancing the north-south divide. Without it, Sheffield and Nottingham will be left as the only core cities without a direct electrified connection to London.
In fact, the midland main line has the best business case of any major electrification scheme, including the Great Western main line. The Department for Transport’s own figures show a benefit-cost ratio of between 4.7:1 and 7.2:1 for the midland main line,
“dependent on train length and train type”,
compared with a ratio of 2.36:1 for the Great Western main line.
Does my hon. Friend think there is a slight irony in the fact that, as he says quite rightly, the midland main line has a better business case than the Great Western main line—and arguably than some of the works on the west coast main line over the years—but electrification of the line has been paused as a direct result of the overspend on the Great Western main line?
I agree 100%. My hon. Friend makes an important point; the midland main line work is paused not because of the business case for the line, which everyone agrees is probably the best of the lot, but because of overspend in other areas.
Again I agree wholeheartedly; I could not have put it better myself. When I go about meeting business leaders, council leaders and civic leaders across the east midlands and Yorkshire, and right up into the north, that point is made constantly.
By now, we are used to hearing about Ministers’ ambition for the north and for the electrification of the rail network, but in reality, in both cases there is a lack of drive to push through the work needed if that ambition is ever to amount to anything. That is why Labour has been calling on the Government to recommence the suspended work on the midland main line and TransPennine routes. Last month, Rail Business Intelligence reported that the Government had instructed Network Rail to “unpause” the electrification of the TransPennine route. As far as I am aware, that is just a rumour, but I would be grateful if the Minister provided some clarification. If true, it would be a welcome development, but of course it raises a question for the Minister: why not the midland main line too?
By calling the suspension “a pause”, the Secretary of State is trying to downplay the potential consequences. The word implies that it will be only a brief time before everything gets going again, and that work will resume as if nothing had happened. In reality, delays in large infrastructure projects always have cost implications—just look at Crossrail. The same story is beginning to play out in this case, too. Philip Rutnam, the permanent secretary at the Department for Transport, told the Transport Committee in July that the principal issue that led to the suspension of work on the midland main line was cost. Network Rail’s initial estimate, in 2013, for the cost of electrifying the midland main line was £540 million. By December 2014, that figure was £1.3 billion. When the work was paused, £250 million had already been spent on contracts for ancillary works, such as rebuilding bridges. Some of Network Rail’s resources have already been transferred to other projects, making it harder and more expensive for the work to get going again. Further delays will only increase the bill.
There are knock-on effects, too. The doubt the suspension has thrown up has led to questions about what rolling stock will operate on the line. There are worries that, assuming electrification does go ahead, the current 1970s-vintage InterCity 125 trains will be replaced by transferred east coast class 91 locomotives, which have poor acceleration; in fact, with those trains, some long distance journeys would take longer than they do at present. So far, the Department for Transport has made no public statement about the specification of the rolling stock that will be used on the midland main line, and I hope the Minister will be able to rectify that.
I apologise, because I will have to leave before the end of the debate, as I have explained to the Chair. On timing, is it not crucial that the high-speed trains on the midland main line are replaced by 2020 because of issues over disability? Equally, Stagecoach’s franchise has just been extended to 2018, but there will have to be certainty about whether electrification goes ahead, because, as my hon. Friend says, that will affect the future rolling stock for the new franchise.
Once again, my hon. Friend is absolutely right.
The recent invitations to tender for the Northern and TransPennine Express franchises have been framed to ensure that they cater for Sheffield’s economic growth requirements. However, it will be possible to meet those needs only with additional diesel-powered rolling stock made available from recently electrified routes.
The ongoing uncertainty over the future of the midland main line work is putting other projects in jeopardy. Those projects go beyond just the midland main line electrification. Some involve improvement works, which are to be delivered alongside electrification. Some £200 million has been set aside for improvements such as the remodelling of Derby station, the straightening of the curve through Market Harborough station and the four-tracking of the line from Bedford to Kettering and Corby. The Secretary of State has suggested that those works could go ahead independently of electrification, but the Department has failed to clarify whether they are still to happen.
There is one final side effect of the suspension. Skills providers have been gearing up to provide apprenticeships associated with the upgrade work, but those are now in doubt too. When the Select Committee asked the Secretary of State about that, he said that, although he was not able to give a precise number for those affected, he felt it was a key point, and he hoped to be in a better position to answer the next time he appeared before the Committee. I do not wish to usurp the Committee’s role, but is the Minister aware of any progress that has been made in quantifying the impact?
I do not wish to rake over the next point, but it is worth repeating that the Secretary of State had plenty of warning that the electrification projects were likely to run into substantial difficulties. As early as June last year, Network Rail told the South Yorkshire Passenger Transport Executive that there would be difficulties in getting the midland main line work done to the relevant timescale. Last year, as a matter of urgency, the Secretary of State commissioned a report on the state of Network Rail’s electrification programme, which he received in September. The Department has refused to publish the report, so we can only assume that it contained warnings of future problems.
In November, Network Rail began to compile a list of the projects at risk. In January, the Select Committee gave an explicit warning about projects being announced without a clear idea of where the funding would come from. It is vital that the Government get a grip on the situation. The Secretary of State has said he is waiting for Sir Peter Hendy’s review, but while he waits for it to give him a solution, the problem is getting worse. He needs to provide a clear commitment to restart work on the midland main line as soon as possible, and that should be backed by a clear timetable under which the project will resume. Otherwise, the uncertainty will mount, and, for all the talk of ambition, the very real fear will remain that the pause will turn into a cancellation.
We need only look at the Hendy review’s terms of reference to see that that is not scaremongering. The review states that
“work that cannot be afforded, or is not deliverable, between 2014 and 2019 is profiled for delivery beyond 2019”—
and then, the key phrase—
“pending availability of funding”.
Taken by itself, that might be dismissed as back covering, but taken with the Department’s recent letter to Network Rail, preparing it for further Treasury-mandated budget cuts of potentially £1.5 billion, it suggests that the ground is being quietly prepared for cancellation. Assuming the rumours about work on TransPennine restarting are true, I am left wondering whether that project has been saved to provide talk about the northern powerhouse with some credibility, while the midland main line is to be ditched as too costly.
I am delighted to serve under your chairmanship again, Sir Roger. I am pleased to be able to contribute to the debate, and I congratulate the hon. Member for Sheffield, Brightside and Hillsborough (Harry Harpham) on securing it. I was interested that he covered the costs involved in pausing work on the midland main line route, as well as the environmental aspects. I was also pleased that the hon. Member for Sheffield South East (Mr Betts) mentioned the extension of the East Midlands Trains franchise, which is very welcome. That is good news for the service and it will provide a lot of continuity.
The outcome of the Hendy review into Network Rail spending will have real consequences for my constituents. The line is essential for business and leisure travellers. We are keen to promote tourism in the area, but it will be affected if the service is not as good as it could be.
When it became clear that Network Rail’s programme for railway upgrades was behind schedule, I supported the Secretary of State’s decision to take action to get it back on track and to ensure that it delivered, in a financially responsible way, the improvements passengers want.
Much of the work that is needed on our railways should have been done decades ago. Governments of all hues have let the railway system down. It is a shame it has taken so long to focus on electrifying the majority of Britain’s railways—something that was started in the 18th century.
I agreed that bonuses to Network Rail’s executive directors should be suspended after the organisation failed to meet targets. That went some way to making up for previous years, when the company paid out £1 million in bonuses at the same time as being fined £53 million by the Office of Rail Regulation for failing to meet train punctuality targets. I have to say that, on Monday, every other train was cancelled because of rather poor signalling, which caused a lot of disruption for a lot of people.
With that in mind, I am waiting to see what Dame Colette Bowe’s review says later this month. Later today, like many other Members in the room, I will be meeting representatives of the East Midlands chamber of commerce, as well as local economic partnerships and councils from across the region, to discuss the paused electrification and the potential outcomes of the Hendy review.
In Derby, we have the largest rail forum in Europe, and the business community is understandably nervous about what the review will say about not just the electrification of the midland main line, but the other proposed upgrade projects. While the pausing of the midland main line electrification was disappointing for those of us looking for that long overdue project to get under way, it should not prevent other improvements from being made to the main line, because those can and must be undertaken.
In his statement on Network Rail’s performance before the House on 25 June, the Secretary of State said that better services can be delivered on the midland main line before electrification. Those include a four-track railway line from Bedford to Kettering, which will create a six-path on the midland main line, so more trains will be able to use it—something we desperately need.
Our trains are a victim of their own success, because they are pretty full most of the time. In addition, changing the layout of the tracks at Derby train station to separate the Birmingham and Leicester routes will make a big difference. The only problem I have with it is that we will never go into platform 1—the easiest one from which to get out of the station—again. However, that pales into insignificance against the fact that we will not always have to wait outside the station, which is the only one on the way up from London to Derby where trains wait outside and people cannot get off until they go in.
The hon. Lady is demonstrating that we are mounting a cross-party argument today, with everyone behind it. She is right to mention the other works that are planned. Over the last few years, the journey time to Sheffield has been cut by 10 minutes for less than £100 million—great value. Will the Minister give a commitment today that the other improvement works will continue while the pause in electrification is in effect?
The hon. Gentleman is absolutely right: this is a cross-party issue that is important to all of us. It is important for businesses across the whole of the east midlands that there should be a much better service.
The proposals can clearly help to increase capacity on the main line route and provide economic benefits to the businesses that rely on them. I hope the Minister can inform us whether a clear green light to proceed will be given in the Hendy review. That will allow businesses and investors to make plans about investing in the necessary skills and capabilities needed to implement the improvements, without any concern that the rug might be pulled out from underneath them at a later date.
The business case for the upgrades and electrification remains strong. As well as creating an expected £450 million of economic benefits, the quicker and more reliable service would cut journey times by up to 15 minutes and improve freight access to the network. Numbers on the midland main line have increased by more than 130% over the last 15 years. A further 30% rise is expected in the next 10 years. All of us who travel on the trains will know that it is much harder to get a seat at peak times now.
I am hopeful that the Hendy review will give a clear answer about when electrification will be given the go-ahead again. A lot of companies in the supply chain part of the rail forum in Derby are waiting for the announcement. They need certainty to be able to plan, and so as not to have to reduce their workforce. The less ambiguous the answer, the better, because a lot of work has already gone into the electrification plans—for example, on the advanced design work for electrification and the re-building of a number of bridges. The longer we delay, however, the more uncertainty builds and the higher the costs will be if we decide to go ahead at a later date.
I am happy to continue working with the large number of stakeholders, including our local rail forum, who are looking to see the main line improvement go forward. Pausing it was the right thing to do, but I do not want this to be another project that is kicked into the long grass. I hope the Minister can inform us of when we will know for certain which projects are to be given the green light and what factors are being taken into consideration to determine that.
As I have said, Sir Roger, I have to leave before the end of the debate, as I have a prior engagement, so I apologise to my hon. Friend the Member for Sheffield, Brightside and Hillsborough (Harry Harpham), to the Minister and to you. I will not take up too much time—I understand that other hon. Members want to speak—but I want to re-emphasise some points that I made in interventions.
I remember, when I was first elected back in 1992—a long time ago now—going in the cab of a train down to London and being shown all the problems on the midland main line compared with the straighter and quicker routes on the east coast lines, and eventually, the west coast lines. All the curves and bends prevented the trains from going at maximum speed. Ten years later, I remember going to a conference with Network Rail to talk about how we might deal with the problems on the line; and, another 10 years later, we finally got the upgrade. It was a long time in coming, but, as I said in an intervention, for less than £100 million, we cut 10 minutes off the journey time to Sheffield. When we consider how many billions were spent achieving not much more than that on the west coast line, we can see what good value the midland main line offers when improvements to it are carried out.
That is a good starting point, and it leads on to the point that my hon. Friend has made very eloquently. The business case for electrification of the midland main line is very strong indeed. It is one of the strongest—stronger than that of the great western line, so we have to ask why it was put behind the great western line. Maybe the question of having to replace the rolling stock on the great western line drove that decision and put it ahead in the queue, but it was certainly not the strength of the business case.
That leads me on to issues for the future. Given that we have already delivered track improvements on the midland main line and have progressively, over the years, brought the journey time to Sheffield down to two hours—a long-term objective that we have now achieved—why can we not have a serious commitment from the Minister now that, irrespective of the electrification pause, we can get on with the other track improvements? As I understand it, they will take another 10 minutes off the journey time to Sheffield and mean reductions in the journey time to the stations in between. The Government can do that. They have not announced a pause on those, so can we have clarification that those other improvements will go ahead? Of course we want electrification as well, but this commitment can be given ahead of any decision on electrification. The Minister can do it today.
There are two drivers of this. We have some challenges coming up, the first of which leads back to my point that perhaps a driver of the great western line electrification was the issue of rolling stock. My hon. Friend has already referred to the fact that if we get electrification, we will need the new Hitachi trains to run on the track, because only they will give time improvements with electrification, not the discarded, heavy trains that are currently running on the east coast line. However, the problem is that the HSTs on the route are old, out-of-date and not friendly for disabled people and will have to be replaced because of disability legislation by 2020. Indeed, the HSTs we have are themselves second-hand and discarded previously from other train lines. They were not new trains—most of them—when they came on the midland main line in the first place. There is therefore a big decision to be made. If the rolling stock is to be replaced, what will it be replaced with? The HSTs will have to be replaced because of disability issues, and in my view it will be nonsense to replace them with more diesel trains, thereby effectively locking out electrification for the foreseeable future.
We also have the franchise issue. The hon. Member for Mid Derbyshire (Pauline Latham) referred to the good news, which has just been announced in the last few hours, about the extension of the Stagecoach franchise to 2018. That means we will have a new franchise from 2018, but will it be for an electrified service or a diesel service? Again, the franchisee will have to indicate what rolling stock they will use on the line. They are going to need clarification about the future of the line and electrification in order to make a sensible decision.
For all those reasons, it really requires the Minister to say yes to the track improvements now and to give a clear timetable for the decision on electrification, so that these other factors can be taken into account as part of that.
Thank you for calling me to speak, Sir Roger. I join other hon. Members who have called strongly for the electrification of the midland main line to be unpaused as soon as possible, so that we can have it as close as possible to the original 2020 deadline. I also congratulate the hon. Member for Sheffield, Brightside and Hillsborough (Harry Harpham) on securing this important debate.
Let me say at the start that I understand why the Government felt a need to pause a scheme when they thought costs were spiralling out of control. Those of us who care about the responsible use of public money accept that if things are going wrong and costs are escalating, we have to get them under control and try to get the best value from the amount of money we can spend on such improvements. I therefore do not object to a brief pause to reset Network Rail’s capacity to understand what it is doing, but I do object if that brief pause becomes indefinite and starts to look like a cancellation to those of us who want the line electrified, with electric trains running on it.
As all the other speakers have said, there is a strong business case for electrifying the line, which has suffered from under-investment probably for the whole length of its history. The two competing lines—one to the east and one to the west—have dramatically faster journey times. If I travelled from Tamworth rather than Derby, I could get to London in one hour, rather than an hour and a half. If I choose to go from Newark or Grantham, rather than Nottingham, I can get a journey time of about one hour, rather than one hour and 40 minutes. Those who live east of Nottingham or west of Derby do not use the midline main line, because of the historic under-investment and much slower journey times. There is a clear need for investment in the line to get a service that is comparable to those around it and to give the important cities of Sheffield, Nottingham, Derby and Leicester the sort of rail service they need to attract the economic investment that the area so desperately wants and needs.
As other Members have said, that is a key point for the future of the line. We need to know by 2019 what rolling stock we are buying, because if we end up investing in the long term in diesel rolling stock, it will be much harder to make the case later for electrifying the line. The Government would then be faced with the question of whether to invest in dual-power trains to allow for possible future electrification. That would not be a sensible use of money.
My vision is for brand-new electric trains, built by Bombardier in Derby, operating on this line—I am not sure about those Hitachi things that the hon. Member for Sheffield South East (Mr Betts) mentioned—but if we do not get the decision right now, we could find, when the next franchise is let in 2018-19, that this will have been a long-term decision not to electrify the line, and that would be a very bad decision. If we want the east midlands to be the powerhouse of growth, I want the engine room to be electric, not diesel.
I have another little request. The original plan to electrify the line missed out a couple of stations on a bit of the line through Langley Mill and Alfreton, which is on the Nottingham to Sheffield stretch. It seemed bizarre to electrify most of the line and then miss out a bit. I am not sure what that would do for services from Sheffield to Nottingham. I cannot see that it would do much for the direct trains to London from Langley Mill and Nottingham, which are so valued by my constituents. I therefore say this to my hon. Friend the Minister: as we are looking to unpause this, let us actually do the whole line, not most of the line, and get that little branch line added into the programme.
It is already proving quite hard to sell HS2 to my constituents as a great idea because of the pretty low return on the investment—it is certainly much lower than for electrification of the midland main line. If we have to go to people and say, “Look, a return of £4 for every pound that’s spent isn’t enough. We can’t justify spending this money electrifying this line where you could have nice new clean and faster electric trains and faster journey times somewhere in the early 2020s”—I hope—they will probably not understand why we can spend a hell of a lot more money trying to get a line that would be a bit quicker sometime in the 2030s.
We must be consistent in how we evaluate investment in rail infrastructure. If we cannot afford this project—if we cannot justify it—then those of us who do support HS2 will have a much harder job of trying to understand and explain why we are still doing that. I think all our constituents up this line would say, “We would rather have this scheme and these improvements sooner than wait and hope that we might get an HS2 in 15 or 20 years’ time.” The Minister should be aware that we have to be consistent and clear in giving explanations, especially if rail investment is going through the east midlands up to Sheffield. We cannot have a nice grand project that we struggle to sell while we are not investing in the short-term stuff that we really need.
The hon. Gentleman is making a very important point, and I support HS2 strongly as well. The Government have said repeatedly to people, “Don’t worry about HS2. It will not affect the investment in the rest of the railway.” Are people not likely to conclude that if electrification does not go ahead on the midland main line, that promise of no impact from HS2 is not being kept?
I think that would be the conclusion. People would see money being spent on rail improvements and think that it was all being sucked into HS2 and we were missing out on a much quicker and much more effective scheme, with a much higher rate of return. They would think that that was a somewhat strange decision, at a time when the Government are trying to get more value for money from public spending.
This is a very important scheme. It has a very strong business case. I think that it ought to go ahead. Let us get the pause done, get this re-energised, get a new timetable, which I hope would show completion in the early 2020s, and get the other improvements done. Let us get moving; let us get Network Rail under control, but this scheme should not be cancelled.