Great Western Main Line: Electrification Debate

Full Debate: Read Full Debate
Department: Department for Transport

Great Western Main Line: Electrification

Baroness McIntosh of Pickering Excerpts
Tuesday 14th March 2017

(7 years, 9 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Ahmad of Wimbledon Portrait Lord Ahmad of Wimbledon
- Hansard - - - Excerpts

I thought I was pretty clear, but obviously not clear enough for the noble Baroness. I said that some parts of the electrification have been deferred to Control Period 6, as she is aware. The Government will review the spending on that to ensure the electrification on all remaining parts that have been deferred is in the interests of customers. The Cardiff to Swansea route that the noble Baroness specifically mentioned will be subject to the next control period—CP6.

Baroness McIntosh of Pickering Portrait Baroness McIntosh of Pickering (Con)
- Hansard - -

My Lords, the electrification of the east coast main line route was completed in 1990. We are expecting a massive investment by Virgin Trains East Coast by 2020. At the moment, the line frequently fails. Does the noble Lord have a timetable and an idea of the investment that is required, and when Network Rail might carry out the investment required to ensure that the investment that Virgin Trains is making will be worth it?