(11 years, 5 months ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
On Chippenham station, I am advised that Network Rail had to go through the lengthy planning process to which my hon. Friend correctly referred, which of course also involves building consent. In addition, it has to co-ordinate its plans with other projects in and around the station. However, I am told that that has now happened and that a detailed design for the project is complete. Work is due to start in November this year and to be completed by July 2014. However, I have asked Network Rail to review its time lines to determine whether it can accelerate construction, given the delay that has already occurred.
Given the comments that have been made in the debate and the expectations on train operating companies to build in such facilities described by the hon. Member for Penrith and The Border (Rory Stewart), will the Minister consider giving some guidance on, or commenting about, the extent to which we could build these requirements into the franchising contract documentation and place obligations on the train operating companies to deliver those very facilities?
I want to come on to the various mechanisms through which improvements can be made, but the hon. Gentleman is right to say that, in theory, franchise requirements can be designed to achieve them. However, other methods are perhaps more effective. If I may make some progress, I hope that I will be able to give him some comfort.
Some 104 of the projects under the Access for All programme have already been completed, which is good news, and we expect the majority of the rest of the projects to be completed by March next year, which will be a full year ahead of schedule. The work has included significant engineering work at stations such as Clapham Junction, which is the station with the most daily train services in Europe and is now fully accessible for the first time in its 150-year history.