The hon. Gentleman is right to talk about the integration between Crossrail and Euston and what might be possible at Euston, but does he agree that it is completely mad that HS2, which will be coming from the north, does not go to St Pancras or even connect with HS1 to enable people to travel to the continent?

Andy McDonald Portrait Andy McDonald
- Hansard - -

That point has been raised several times. The intention, as expressed in the documents, is to have a pedestrian connection between them.

An overarching approach to an integrated station would not only take account of all the anticipated works but achieve the objectives of securing the best possible outcomes for the residents of Camden and minimising the enormous disruption they will undoubtedly suffer. Many properties will be demolished and other properties will be in extremely close proximity to the works; public open spaces will be lost; there will be fleets of heavy goods vehicles and commercial vehicles; and noise pollution will undoubtedly disrupt the peaceable enjoyment of many properties, including in places such as Cobourg Street, which is a tranquil community with a quiet courtyard at its heart, notwithstanding its close proximity to busy traffic and the railway station. Businesses in streets like Drummond Street will also be disturbed.

We are asking the good people of Camden to put up with a great deal and to make huge sacrifices for the benefit of the nation, and Labour has tried to do all it can, in new clause 22 and in Committee, to mitigate the impact on the quality of life for residents. We acknowledge the sincerity of the Minister and his colleagues in working to that objective, but we take the view that this is so important that the assurances given ought to be in the Bill and have the full force of law.

We seek to minimise the amount of excavated material and construction materials transported into and around the site by road and to have as much as possible moved by rail. Camden Council has developed a Euston area plan, and we propose that any designs for the enlarged Euston station take full cognisance of that plan and other such framework documents and relevant guidance. The assurances talk of various boards, including the Euston strategic board, the Euston station strategic redevelopment board and the Euston integrated programme board, which bring together a number of prescribed partners. We seek to ensure that the nominated undertaker—the relevant body carrying out the HS2 works—is obliged to participate in those boards, as the assurances given by HS2 so describe.