General CommitteesI beg to move,
That the Committee has considered the draft Nuclear Decommissioning Authority (Pension Scheme Amendment) Regulations 2024.
It is a pleasure to serve under your chairship this afternoon, Dame Maria. The regulations were laid before the House on 19 December 2023.
Lord Hutton’s 2011 report into public sector pensions fired the starting gun on a long process of reform. While the Public Service Pensions Act 2013 made wide-ranging and important changes, it did not cover all public sector bodies, including those within the Nuclear Decommissioning Authority group.
The NDA was created in 2005 as the statutory body responsible for the decommissioning and safe handling of the UK’s nuclear legacy. It has 17 sites located across the UK, including Sellafield in Cumbria, the world’s first civil nuclear power station. That means that Sellafield and many parts of the NDA’s other sites pre-date the formation of the NDA by several decades, leading to a complicated set of pension arrangements, including two pension schemes closed to new entrants in 2008 that provide for final salary pensions, which are in scope of the reforms. These are the Combined Nuclear Pension Plan and the Site Licence Company section of the Magnox Electric Group of the Electricity Supply Pension Scheme.
The complexities of the schemes clearly required tailored reforms, which is why in 2017, the Department for Business, Energy and Industrial Strategy and the NDA worked with trade unions to agree a reformed pension scheme that maintained valuable benefits for its members while bringing it into line with the rest of the public sector. The result was the proposal of a bespoke career average revalued earnings, or CARE, scheme.
In terms of timing, before bringing forward the provisions we required primary powers in the Energy Act 2023 before secondary legislation could be brought forward. I appreciate that the process has taken rather longer than hoped, but we are confident that the reform will yield financial savings, bolstering the NDA’s mission of responsibly decommissioning the UK’s nuclear legacy.
Following statutory consultation with NDA employees and a ballot of union members, the CARE scheme was formally accepted by the trade unions. A formal Government consultation was launched in May 2018, with the Government publishing a response to the consultation in December 2018, confirming the proposed changes. Now, thanks to primary powers introduced in the Energy Act 2023, we are able to bring secondary legislation forward.
The reformed scheme offers excellent benefits to its members. Unlike most other reformed schemes, it still includes provision for members to retire at their current retirement age. For nearly all, that will be 60—most other public sector pension schemes only allow a full pension at 67. Once the CARE scheme is introduced, contributions will increase on average by 3.05%, phased in over three years.
A statutory framework that applies pension benefits across the NDA estate meant that specific legislation was needed to implement this reformed scheme. This secondary legislation is being made to require NDA and Magnox Ltd to amend the relevant NDA pension schemes and implement this CARE-based pension reform. It will also modify the statutory pension protections contained in the Energy Act 2023 and the Electricity (Protected Pensions) (England and Wales) Pension Regulations 1990, in support of the reforms.
These measures will make the NDA group’s final salary pensions fairer and more efficient by aligning them with wider public sector pensions. They will also deliver crucial savings to the NDA budget at a time when it is needed, more than ever, to support the decommissioning of this country’s proud nuclear legacy.
I thank the shadow Minister and my hon. Friend the Member for Amber Valley for their questions. The hon. Lady asked about the time it has taken for us to bring the changes forward. She is absolutely right: it is sub-optimal that it has taken this long. Having met the unions in the latter part of last year, I am aware of the concern and the not inconsiderable worry caused by how long it has taken us to bring this forward. However, we did need to wait for parliamentary time and the actions that we brought forward through the Energy Act to allow us to make the changes required to bring the NDA’s pension schemes into a much better place than where they were.
It should be recognised that the pension is very good. Allowing a full pension award at 60 for the majority of members when most public pensions are linked to a state retirement age of 67, as my hon. Friend the Member for Amber Valley mentioned, was a considerable win for workers at the NDA and something we are proud to have achieved. It means that the Nuclear Decommissioning Authority—a vital part of our effort to maintain a safe, sustainable nuclear estate in this country—will continue to be attractive to the best and brightest. We all agree that that should be an ambition.
The NDA will, of course, continue to engage extensively in communicating the reform to employees affected by the changes and the trade unions that provide representations across the NDA group. Of course we are always happy to look at the impact of the changes once they have been implemented. There is the ability after the implementation of this secondary legislation to make changes to how the schemes operate.
Did the Minister address the point about the £200 million savings or did I miss that?
No, the hon. Lady is absolutely right. Sorry, I had forgotten that she asked. There will be significant savings, of course, for the NDA and that is a good thing. We have reached a good settlement on the new pension scheme. It is a good pension for members. We will continue to attract the brightest and best into the organisation and give people certainty about where they are going to be when they hit retirement age, while providing significant savings for the Nuclear Decommissioning Authority, which will allow it to carry on with its important work for this country, at Sellafield and the other nuclear sites in which it is engaged across the UK. That work is only set to grow, by the way, as more of our civil nuclear fleet reaches the stage of having to consider moving into decommissioning mode. The NDA’s work is about to increase exponentially so the savings made by the changes will be important and allow it to do more and do it effectively.
The Government remain committed to ensuring that pension schemes are fair, efficient and in line with the wider public sector. The regulations are essential to the successful implementation of a CARE-based pension reform of the NDA group. Crucially, they preserve commitments to excellent benefits, including provisions for members to retire at the current retirement age. They also yield financial savings that will be used to bolster the NDA’s mission of responsibly decommissioning the UK’s nuclear legacy. I urge the Committee to support the draft Nuclear Decommissioning Authority (Pension Scheme Amendment) Regulations 2024.
Question put and agreed to.
2.41 pm
Committee rose.