Alan Whitehead
Main Page: Alan Whitehead (Labour - Southampton, Test)(3 years ago)
Public Bill CommitteesQ
Richard Hall: Yes, certainly, Alan. There are good reasons to think that a RAB model could reduce the cost of capital associated with bringing forward new nuclear projects, but it is important to be mindful that consumers are not simply exposed to the cost of capital; they are also exposed to the volume of capital. That is relevant in the case of nuclear because nuclear projects have a track record of coming in over budget and behind schedule.
If you look at the impact assessment that the Department for Business, Energy and Industrial Strategy published alongside the Bill, it highlights that, on average, new nuclear projects of the nth of a kind—not the first reactor of a particular model to be built, but an iteration of it—have come in 20% over budget within Europe and 100% over budget worldwide since 1990. It also highlights that nuclear projects within Europe have suffered construction time overruns averaging 40% following the final investment decision. The average is 90% on a worldwide basis since 1990. This matters to consumers because, under a RAB model, unlike a contracts for difference model, they are exposed to the cost overruns and to the time overruns if they occur in a different way.
Perhaps to unpack what we mean by that, I should point out that under the CfD model that was adopted for Hinkley Point C a price is guaranteed to the developer for every megawatt-hour of output it produces, and that is inflation-linked, but consumers do not become liable to start paying those costs until the plant is operational. Those costs are pay on delivery. Consumers are not expected to pay in advance of the plant being there. Under a RAB model, consumers would start paying towards the cost of the plant from the time the construction commenced. Indeed, the Bill as it is drafted allows for that. If there are construction cost overruns, consumers will essentially be paying for a benefit in terms of a production facility that is not actually being delivered yet. That is the point about construction time issues.
On cost overrun issues, while the strike price that was agreed for Hinkley Point C appears to some commentators to be quite high, it has the advantage to consumers of being, in effect, an all-in price. If the cost of the build project escalates over time, those escalating costs will have to be met, but they would be met by the developers; they would not be met by consumers. Essentially that risks sits with investors. Under the RAB model, however, it is likely that any cost escalations would be shared between the consumers and investors. At this stage, we do not know exactly how. The BEIS consultation from the autumn of 2019 suggested that it might look at putting in place mechanical sharing factors between the developer and consumer. That means if the construction were to run under or over budget, a proportion of the benefits or additional costs would be borne by the investors and the developers, but a proportion would also be borne by consumers. On that, it is important to be aware that although the developers have some control over construction because they are in control of the overall project, consumers do not have any control over the risk. Essentially, they are the passive recipient of the risks.
In a nutshell, the concern that we have is that if a project were to come in on budget, RAB looks like a very good model potentially, but there is a strong historical track record that suggests that projects may not come in on budget. Under the RAB model, consumers may be exposed to significant cost overruns as a consequence.
Q
Richard Hall: There is a lot in that question. I will try to unpack it if I can—there was something about methods of financing, and something about cost caps too. Regarding cost caps, the Bill envisages that there would be a funding cap essentially—a point at which, if costs escalated significantly above the expected spend, the Secretary of State would be prompted to take a decision on what should happen with those additional costs. I do not believe that the face of the Bill actually stipulates what that materiality would be, and I think it also leaves that decision very much at the Secretary of State’s discretion, so there is the potential that they could simply acknowledge that there was a problem, but continue to put those costs on to consumer bills. That seems to be fairly vague: it leaves room for ambiguity on what a Secretary of State might do in that type of scenario in future.
A couple of things could be done to try to mitigate consumer costs. The first is that the sharing factors that are set out—they are not set out in the Bill; they are to be agreed between the Department and the developer, as to who bears the costs if there are significant cost overruns—should be slanted towards the developer facing most of those costs. Again, that is because consumers have no ability to control those costs whatsoever, whereas the developer does have the ability to control some of those costs. Effectively, that risk needs to be borne as much as possible by the developer. It should be borne in mind that, obviously, that creates some interactions with the cost of capital: effectively, the more you de-risk the developer, the more you reduce the cost of capital, but given that you are only doing that by pushing those risks on to consumers, we think it is probably better to ensure that the developers are subject to as sharp incentives as possible to build it on time.
Turning to the other areas that I think would be of assistance, the Bill envisages that the developer would have a right to appeal any decisions that Ofgem made on the price control that had been agreed for the developer. Intuitively, those appeals are only going to go in one direction—that is, if the developer feels that a settlement is not generous enough to it. It is hardly going to appeal if it feels a settlement is too generous. I notice that elsewhere, in terms of many aspects of energy governance, where appeals processes exist, they are bidirectional: they allow for someone to appeal that a settlement is too tough, but they also allow for people to appeal that a settlement is too weak. We think that type of approach should be followed here: if the developer has the right of appeal to basically ask for more money, other interested parties should have the right of appeal to argue that there should be less money, so there is bidirectional scrutiny and tension there.
A second area in which I think we could help to bear down on costs is that it is quite important that some form of independent third-party impact assessment is made of the key terms of any deal that is agreed under this Bill, and published before that agreement becomes legally binding. I would also like parliamentarians such as yourselves to have an opportunity to see the headline terms of any agreement and that independent third-party impact assessment, and to be able to scrutinise those costs before the agreement becomes legally binding. If that seems like it might be quite an unusual thing to do, because obviously Parliament does not micromanage individual infrastructure purchases, we would argue that it is justified in this case, because we are talking about building assets that will—even at the most conservative estimate—cost consumers tens of billions of pounds, and those costs will be recovered from consumers for potentially 50 or 60 years.
Q
Richard Hall: On those two specific projects, Heathrow and Thames Tideway, I cannot give any insight. I am not particularly close to those individual cases. It is fair to note that in both cases the cost of capital brought forward by the model seems to have been low, in particular in the case of Thames Tideway. On nuclear, I simply go back to the point that there is a large base of literature looking at historical cost overruns and the extent to which things come in on budget. That tends to display fairly consistently that these types of projects are very likely to be subject to optimism bias at the time that they are procured—a belief that they will be cheaper than they actually will be.
In addition to the costs and dates I mentioned from the BEIS impact assessment suggesting the average levels of cost overruns, look at a couple of other examples from academia: Sovacool et al. looked at a global example of 180 new nuclear plants and found that 97% of them came in over budget and that the average cost overrun was 117%; and Flyvbjerg et al. found that in a sample of 194 nuclear plants, the median cost overrun was 68% and the median schedule or construction-time overrun was 40%. That is a fairly large sample set of projects, and the analysis tends to suggest considerable optimism bias for new nuclear—it tends to come in late and over budget.
Q
Richard Hall: Yes, certainly. Paragraph 4.2 of the impact assessment sets out a range of tables showing what the estimated construction and financing costs would be for a Hinkley Point C-sized power station in a range of scenarios: under a CfD with 20% cost overruns, or with 100% overruns, or under the RAB model at various different costs of capital—
Order. I am afraid that that brings us to the end of the time allotted for the Committee to ask questions. On behalf of the Committee, I thank you very much, Mr Hall.
Examination of Witnesses
Chris Ball, Dawn James, Cameron Gilmour and Alan Woods gave evidence.
Q
Cameron Gilmour: I am largely in agreement. I will reinforce Alan’s point about the need for certainty, where any developer or investor needs a programme. When we create a programme, whether it is gigawatt-sized or SMRs, we create that confidence, the continuity of resources, and then we start to see the efficiencies flow through in the programme as we deliver them, whether it is factory or site construction.
Q
Alan Woods: We actually challenged the IAEA on its definition. The response we got was that, at the time it defined an SMR, that was halfway between what it classed as a medium reactor and a small reactor. There was no set rationale for why it classified, and it was many years ago, that 300 MW. The simple reason that ours is 470 MW is that we set a requirement on the design to be road transportable. Each module has to be transportable to site by road. That gives us maximum site flexibility. It also removes the need for expensive additional infrastructure, such as new port facilities or new roads, to get the parts in.
Having set the size for the biggest module to be road transportable, the biggest limitation across Europe is about a diameter of 4.5 metres for the biggest module. If we set that as the maximum size for our reactor pressure vessel, that gives us an internal diameter and an internal volume for that pressure vessel. Using conventional available fuel that is made today in the UK and elsewhere, that sets the power that we can get out of that pressure vessel, so we need to design around that power.
The objective that we had, which was set by the utility partners we have worked and continue to work with, was that they want the maximum power for the least capital cost. We are therefore delivering that within the constraint of road transportability.
Q
Alan Woods: Yes; all new plants that come to the UK have to go through the generic design assessment process. We put in our application to enter that process last week.
Q
Alan Woods: Our next phase of the programme is for the next three and a half to four years, which will get us to the end of GDA step 2. That is the point at which we have completely de-risked it—not that we see any risk to going through the regulation, because as I said, this is proven technology power plant. We have already been working with the regulator for some time. At that point, we move to the final step, which is step 3, and that will take about another 18 months.
Q
Alan Woods: We would actually start building ahead of that, because the GDA process allows us to prioritise the longer-lead items, the critical items, up front. We validate those with the Office for Nuclear Regulation early, on the basis that we can then get a release to order to accelerate the manufacturing process. We can do some of that activity in parallel by the way that we sequence the assessment through the GDA activity.
Q
Alan Woods: No, it is eminently possible by the 2030s; it is very doable.
Q
Chris Ball: If we work on the basis that Hinkley C is on line in let’s call it five years from now, we would have an issue if we held back over that time and thought that we then just move across. Naturally, within any project there is a phasing—there is a phasing of skills which means that we need to maintain a continuity almost at a lower level in terms of the breakdown of those skills. In my own organisation we currently have of the order of 600 people mobilised on Hinkley Point C. At this point in time, that is largely connected with civil engineering, civil design, design of structures, and that positions us quite clearly in a good position for future export markets. Those skills start to demobilise 12 months from now. Naturally in any major project such as this, civil engineering design is one of the earlier phases of the project. We will start to demobilise those skills 12 months from now, if not sooner, and you would probably say that we would demobilise three quarters of that skills base over the course of the subsequent 18 months. We are talking of a one year to two and a half year period over which we would be demobilising three quarters of our workforce, and taking skills out of the industry.
We would look at other neighbouring industries that have a demand on common skills bases to ensure that we maintain employment where possible, but it still represents a loss of capability from the industry that we may or may not be able to bring back in at some future point. That 12-month period from now is what is high on our mind.
Q
Alan Woods: Chris made the point earlier that net zero is such an enormous challenge. We often think about decarbonisation in the context of the grid, but the grid in the UK in particular represents about 20% of the total energy we use. The rest of it is heat and transport. As we look to decarbonise heat and transport, there are not that many routes available, certainly in some of them. Hydrogen is one, synthetic fuels is one and of course more electrification, but the common denominator among all of those is that you need more clean electricity. The scale is enormous. We therefore welcome any financing mechanism that will help any industry, not just the nuclear industry, bring forward those clean technologies, because the reality is that we have to have them if we are going to meet net zero.
The implications if we are not innovative with how we approach financing both in nuclear but also in other industries mean that we become dependent on other sources of technologies—imported technologies financed from overseas, which bring with them the whole dependency on other nations for our critical energy infrastructure. Increasing that dependency puts our ability to meet net zero at more and more risk.
Chris Ball: I will take a step back here. Earlier, I mentioned that there is a need for about 9 GW a year of construction to take place each year for the next 30 years. We need to find a way of building everything we possibly can in a way that is most cost-effective for the consumer. In every single area, there will be challenges for us to overcome.
People talk about offshore wind at £40 per megawatt-hour strike price. Actually, when it comes to the last two offshore wind farms—one up in East Anglia and one in Hornsea—one was at about £120 and one at £140 a megawatt-hour initial strike price. I recognise that offshore wind prices have been coming down; that is because of consistent underpinning Government policy. We have to replicate that in each and every one of these areas.
Just because offshore wind prices have come down, does not mean that they will continue to do that; they will reach a plateau and companies will start to go to deeper waters and floating offshore wind prices will pick up. We are also judging things on an old-fashioned measure of the levelised cost of electricity, but for renewables we need to start building in the cost of energy storage as well. That does not come cheap. There is a lot of talk about hydrogen, but that requires a lot of power. For every electron that goes into generating hydrogen, we might get 0.3 electrons back out again; it is not a one for one. That is quite often lost in the debate. Actually, I am a supporter of all these technologies; what I am saying is that we need to look at how we manage those risks.
Net zero will not be achieved without nuclear. From an engineering perspective, the system requires firm power on the grid. The RAB model is a good way of driving forward large-scale nuclear for the benefit of the consumer. Look at the levelised cost of electricity at, let us say, £40 per megawatt-hour for wind, noting my earlier comment, and add the storage costs; if you compare that with nuclear and the RAB model, the prices are very similar. Obviously, Alan also knows the SMR nuclear market very well and would say that, yes, it is similar there.
It worries me that if we do not find a way of pushing all these technologies forward, including carbon capture and sequestration and the technical challenges around that, the risk of failure for the 2050 net zero system is very high.
Thank you very much for attending, all of you. Could Members please indicate to me whether they have any questions to the panel? Dr Alan Whitehead.
Q
Tom Greatrex: Apologies, but I missed part of the question; it cut off partway through, but I think I got the gist in relation to Chinese investment in UK nuclear. I think that is what you were asking about—is that correct?
Yes, basically.
Tom Greatrex: You will recall, I am sure, the original arrangements that were made to facilitate Chinese investment in UK nuclear. China General Nuclear, who are currently the minority financial shareholder in Sizewell C, are also a member of the Nuclear Industry Association and have a potential project at Bradwell. In terms of technology, it is very clear that any reactor technology has to go through the same process to be approved, and that is done independently by the Office for Nuclear Regulation. I do not think there is any difference in the thoroughness of that approach, wherever the technology comes from.
However, making decisions on the larger geopolitical issues is, I am afraid, way above my current—or ever anticipated—pay grade. As far as I am concerned and as far as the industry is concerned, Chinese companies have significant expertise in nuclear capacity and have built quite a lot of nuclear capacity, working with different reactor designs in China. Whether, and to what extent, they should be involved in the UK is not really for me to express a view on.
Q
Tom Greatrex: In terms of that funding being available, for a number of years, the Nuclear Industry Association and companies that we represent have made representations to Government about the costs associated with large-scale projects prior to getting to final investment decision. Significant amounts of money were spent on projects that have not happened during that process, and that pre-development funding is something that needed to be considered.
As to what that announcement covers, we have asked Government for further information on that. At the moment the information we have is that that is funding that could be available to a range of different projects and opportunities, but nothing specific. In relation to what I think was your implied question, on whether this is instead of buying out the CGN stake in Sizewell, it has not been made clear to us that that is what it is for.
Q
Tom Greatrex: Yes, we have had the announcements and spoken to officials about the announcements, but we do not have any more detail than is currently available.
Q
Tom Greatrex: Well, I hope that there will be clarity on that and other aspects of what has been announced by the Government in recent announcements as we proceed.
Q
Tom Greatrex: The Bill sets out a framework for a mechanism that we as the industry welcome. We think it is very important to be able to facilitate development of new projects. There are levels of detail that are not covered in the primary legislation, and I think you have touched on some of those in relation to exactly how aspects of risk sharing will be undertaken and the role of the regulator, which will be Ofgem—the expertise available to that body, and the fact that transitioning into being able to undertake what is effectively a new role is going to be significantly important. I am not sure those would necessarily be in the primary legislation, but there are aspects of this where there will need to be further information and development before a regulated desktop-based model can be used for nuclear development.
Q
Mycle Schneider: Yes, I can briefly comment. I think you are referring to the V.C. Summer plant in South Carolina. It had a similar scheme to RAB, which basically allowed it to pass on cost overruns to electricity customers. Construction started in 2013. Westinghouse was the technology provider. The plants were supposed to come online in 2017. By 2017, the cost estimate had increased by 75%, and I believe that there were nine rate increases for ratepayers up to that point. Finally, in July 2017 the construction was abandoned. Obviously, this was one of the consequences of the fact that Westinghouse filed for bankruptcy, and one of the main reasons for that was the V.C. Summer AP1000 project.
It might be interesting for the Committee to spend some time studying this case because it also involved some very problematic criminal activity. The federal grand jury has charged the former senior vice-president of Westinghouse Electric Company, Jeffrey A. Benjamin, for his role in failing to report accurately the status of the construction of these nuclear sites. It is worth noting that he served as senior vice-president for new plans and major projects, and was therefore directly responsible for all new projects worldwide for Westinghouse during the period of the V.C. Summer project. He has been charged in a federal indictment with 16 felony counts,
“including conspiracy, wire fraud, securities fraud, and causing a publicly-traded company to keep a false record.”
That is a quote from the Justice Department. He is only one of four top managers who had criminal charges filed against them in this affair. The former chief executive officer of SCANA, the utility that was building the plant, pleaded guilty to federal felony charges and was sentenced to two years in jail, which will start in December. The case had major implications.
Obviously, the ratepayer is left with the ruins of concrete and steel, and with no kilowatt-hours. Apparently, reportedly this affair is not over. It has cost the ratepayers billions, and reportedly it will cost more over the 20 years to come.
A number of Members want to ask questions, so could we keep them as short as possible?
Professor Thomas: I wanted to add that what marked out the Summer project and a similar project in Georgia from those in all other states of the United States was that they were allowed to recover money from consumers before completion of the plant. That is a central feature of the RAB proposal. The Summer experience shows clearly the folly of making consumers pay for a plant before it is complete.
We have to be careful with the idea that we need to take measures to prevent unfinished plants from being abandoned. We have a very good example in Britain in the Dungeness B plant: it took 24 years to get from start of construction to commercial operation, and over its 32 years of operating life, its availability was well below 50%. It is very clear that the plant should have been abandoned before it was completed.
Doug, do you have any comments?
Doug Parr: I am not sure that I have much to add. I read that the Summer plant added 18% to bill payers’ bills in South Carolina at one point, which is obviously a very considerable amount. I am not saying that those numbers are translatable to the UK context. It chose to expose the consumer to those considerable risks.
The Government really need some kind of independent evidence base for their judgments if they are going to enter bilateral negotiations with a plant builder who, on the basis of the plant builder’s word, can expose consumers to very considerable risks; Dr Schneider alluded to that. We see that with the RAB mechanism, the Government have a bilateral negotiation mechanism, and those do not have a happy history in almost any sector, including for the various networks. I am not quite sure how you establish that.
One thing that has been missing from nuclear policy as it applies to renewables and other mechanisms, such as the capacity mechanism, is the element of competition. The information asymmetry is potentially very strong. It gives a lot of cards to the nuclear seller—the nuclear provider—without giving the Government any backstop with regard to understanding what is going on. When there is competition via a reverse auction of the kind that we find in renewables, you factor those risks out, but consistently over the years—decades, in fact—this kind of discipline has not been applied to nuclear policy. With the RAB-type mechanism, those risks potentially land on the bill payer, not the provider of nuclear stations.
Q
Doug Parr: I am not sure that I am across the detail enough to give a good answer to that one, I’m afraid. I would need to come back to the Committee on that, if that is all right.
Q
Professor Thomas: I think the problem is not the need for a special administrative regime to rescue things if it all goes badly wrong in the construction phase. I think the problem is the RAB mechanism that is putting consumers’ money at risk, and if we look at the impact assessment, we are looking at a plant that will not be completed until something like 2037 to 2041, so I will be paying into this plant for quite a long time and I probably will not live long enough to see any power from it. The special administrative regime is a way to try to solve a problem that is better solved by simply not using this RAB mechanism.
Q
Doug Parr: I do not think I have ever made any secret of the fact that there are attendant risks that come with nuclear that do not apply to other forms of zero-carbon and low-carbon generation. What I would ask, in the light of the climate crisis—it is not an insignificant challenge that you have put there—is why UK Governments of all colours have continued to emphasise nuclear policy over and above other ways of cutting emissions. For example, the last time I saw figures on Department for Business, Energy and Industrial Strategy civil servants and where they were working, there were more people working on nuclear than on renewables and clean building heat put together, so when it came to two of the big-ticket items that are going to be absolutely essential—lots of renewable power and lots of clean heat for buildings—there were fewer civil servants working on those than on nuclear.
Nuclear is a bit-part player in this. All sensible, cost-effective models show that nuclear will not be a big piece of the pie, in terms of delivering what we need to deliver, and there are considerable problems with delivering heat, as members of the Committee will know. There are some substantial issues with delivering the amount of renewable power that we need, yet what we have is a Bill for delivering nuclear, and more civil servants working on it than on other things. I emphasise that this is a distortion that has been in place over years, and it is becoming quite problematic, because every time people are working on nuclear and not working on these other things—not putting energy and money into other things—we lose our ability to deliver what we need to deliver.