East West Rail: Bedford to Cambridge

(Limited Text - Ministerial Extracts only)

Read Full debate
Tuesday 13th June 2023

(1 year, 5 months ago)

Westminster Hall
Read Hansard Text

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Huw Merriman Portrait The Minister of State, Department for Transport (Huw Merriman)
- Hansard - - - Excerpts

It is a pleasure, Sir Mark, to serve under your chairmanship this afternoon. I thank my hon. Friend the Member for North East Bedfordshire (Richard Fuller) for securing this important debate on East West Rail from Bedford to Cambridge. I have listened carefully to his representations. As everyone in the debate has said, he makes excellent points and sets us a challenge. I am keen to work with him to address those points.

I have noted the six or seven points he raised. I will go through some this afternoon, but I will write to him on all of them. I want to work with him to ensure the project is delivered in a way that maximises benefits for members of his constituency and the country as a whole. I am well aware that, when it comes to building new railways, some are very much in favour because they benefit directly or indirectly from the delivery of that new railway. We will always call for infrastructure to be delivered before housing. This is an opportunity where that can be delivered.

Of course, there are those whose lives are directly impacted and blighted by railways, who suffer as a result of the build. I have every sympathy with them, and I am keen to work with my hon. Friend and other hon. Members to minimise that and to give as much information, clarity and frankness in the process as we can. I say that as someone whose family lives in Buckingham and is well aware of the impact of HS2. “I get it,” is what I want to say this afternoon.

Let me speak a little about the project and then go into detail as I go along. The East West Rail project will improve the UK economy, supporting ambitions for the Oxford to Cambridge region, to add £103 billion extra gross value added by 2050, securing the UK’s future as a world leader in science and technology. East West Rail will improve connectivity and ensure growth is spread across the region as a whole. The route update announcement, which was mentioned, was laid before us on 26 May, and set out the preferred route alignment between Bedford and Cambridge. That would serve new stations at Tempsford and Cambourne, and approach Cambridge from the south, enabling services to call at the new Cambridge South station and to serve the world-leading biomedical campus. As my hon. Friend the Member for South Cambridgeshire (Anthony Browne) mentioned, I was at the site a couple of weeks ago. It is absolutely fantastic; people are incredibly excited about what this railway will deliver through not just better connectivity but allowing more jobs to flow to the campus, enabling it to succeed and to take on the world’s finest. I am very excited to have been able to announce the funding.

The route update announcement is a milestone that reaffirms the Government’s commitment to the project, along with funding of £1.3 billion to deliver the first connection stage of East West Rail between Bicester and Bletchley. It is part of our national commitment to unlock transformative growth within the globally renowned Oxford-Cambridge hub of science, research and technology. It will transform connectivity for residents and businesses in addition to supporting economic growth and local housing plans. Again, I acknowledge the challenge that housing can deliver in that particular part of the country. The support from Cambridge University, biopharmaceutical companies such as AstraZeneca, Oxford University science park and local enterprise partnerships across the route demonstrates the confidence that key stakeholders and businesses have in the benefits of East West Rail.

With every project at this scale, important decisions must be made to optimise and maximise the benefits it can provide. The proposal to build new stations at Tempsford and Cambourne will enable communities to grow, provide opportunities to improve biodiversity and give people increasing access to green spaces, significantly outweighing the benefits that a St Neots station could provide. As I have stated, I recognise that the proposals will have an impact on some homes and businesses. In particular, I understand the concerns of residents immediately to the north of Bedford station.

The hon. Member for Bedford (Mohammad Yasin) mentioned a six-track rather than a four-track proposal. That is being put in place to regulate the disruptive performance on the existing Midland main line, as well as to mitigate congestion and provide options for future growth. It is an example of where we are building for the future, not just through East West Rail, but to deal with a spot of disruption that already exists. By going to the six-track proposal, we will deliver better infrastructure and a better service on both of those lines, though I do recognise that it has more of an impact on residents.

For local residents who are affected, East West Rail Company has launched a need to sell scheme, designed to support residents who have a compelling need to sell their property but are unable to do so other than at a substantially lower value because of the railway. On the point made by the hon. Member for Slough (Mr Dhesi) that I should meet the hon. Member for Bedford, I did that very recently. We discussed the case of one of his constituents and were able to talk about a solution. I continue to make myself available to all hon. Members on behalf of their constituents who are impacted.

East West Rail Company has also proposed to provide a new relocated station building at Bedford Midland, which will offer opportunities for local authorities to partner with East West Rail to deliver a destination station, if supported by third-party funding. Alongside that, the existing Bedford St Johns station will be relocated so that it is closer to Bedford Hospital, providing better connectivity for patients, hospital staff and visitors. Proposals for East West Rail will also mean a significant investment in the Marston Vale line between Bletchley and Bedford to provide a step change in the frequency of services.

As the House and my hon. Friend the Member for North East Bedfordshire will know, East West Rail Company is holding public information events to answer the questions that have been raised by Members on behalf of their constituents. It is also meeting with stakeholders along the line of route. I will take some of the questions that have been posed, particularly by my hon. Friend the Member for South Cambridgeshire about the design stage, and get responses to them.

A statutory consultation is planned for the first half of next year, in which the next stage of technical and operational design proposals will be presented alongside plans to mitigate any associated environmental impacts. East West Rail Company has committed to delivering a 10% biodiversity net gain across the entire project, and traction options such as full electrification along the whole line of route are currently being reviewed.

Phase 1, which goes from Oxford over to Bletchley, is a mix of an existing line and one that once was a railway line. Phase 2, from Bletchley to Bedford, is an existing line. In that sense, electrification is a more difficult challenge, because bridges and other infrastructure are already in place and would have to be significantly changed. Where we have built new bridges and infrastructure, we have done so with electrification for the future in mind, so there is that pathway available to it. Of course, we are looking toward hybrid options in future as far as trains are concerned, which would enable a better, decarbonised line of route. I know all hon. Members have mentioned that point.

The business case was also referenced. As is standard for a project of this size, a final business case will be put forward once planning consent is secured. Before then, a development consent order application will be prepared in accordance with the Planning Act 2008. East West Rail demonstrates the Government’s commitment to supporting growth and improving connectivity for people and business across the Oxford and Cambridge region.

Let me come to some of the points that were raised—my hon. Friends worked hard to raise as many as they could. The first question was, will I walk the line of route? I am not sure whether that is an invitation to walk the entire line of route or selected parts of it, but I am certainly able to say yes to the former—sorry, I should say the latter. I should get that right for Hansard. Yes, I will walk parts of the line of route so that my hon. Friend the Member for North East Bedfordshire can show me the areas that are impacted. Indeed, we did something similar when we looked at the options of coming into Cambridge from the north or going from Cambridge to the south, and I will of course do that in my hon. Friend’s constituency.

My hon. Friend mentioned the new Mayor, Tom Wootton. I met him and he laid out his arguments as to why he believes the line of route should come through the south rather than the north of Bedford. I have said I will write back to him to explain our thinking behind that and I am very happy to continue to liaise with him. We need to ensure that our case is the strongest case and cannot be rebutted, and that it is not only open and transparent but subject to challenges that will make it more robust. I am very keen to do that.

My hon. Friend also asked whether the National Audit Office will conduct an inquiry. We can consider that option. I always enjoyed working with the NAO when I was Chair of the Transport Committee; it has a lot of value to add when it comes to ensuring projects are built to time and cost. External assurance is provided by the Infrastructure and Projects Authority, whose next review is expected before the statutory consultation. It works as an external review body for the project.

My hon. Friend asked whether I will instruct East West Rail to release the maps. We can check what further information and detail can be provided. East West Rail does not yet have a detailed design for every single area, but where it has the details, it will publish them. It has done so in the Poets area of Bedford. I am very keen that we do that at the earliest opportunity to give residents and businesses impacted by the line as much clarity and detail as possible, so I will look at that point for my hon. Friend.

My hon. Friend’s fifth point was about writing to property owners about the current corridor. East West Rail has written to property owners about the route update announcement and will engage with them further in the lead-up to the statutory consultation. Again, I am committed to ensuring that more detail is provided. I will come back to my hon. Friend on all those points and the one or two that I have not addressed because I have not had the time.

The hon. Member for Cambridge (Daniel Zeichner) asked how much money has been spent on the Oxford-to-Cambridge road that was proposed and then stopped, and how many officials are still working on it. I can tell him that £28 million was spent on the development project, and there are no officials working on it right now. I hope he is impressed with that transparency and immediacy.

My hon. Friend the Member for South Cambridgeshire asked who will be responsible for producing the business case. It is East West Rail in partnership with the DFT. We will work closely with the Treasury to make sure that is properly done in the manner that one would expect. There was talk of the theory of change exercise. That methodology is validated by the Government. We have previously discussed the fact that the Green Book is not particularly good at taking into account regeneration and decarbonisation. Changes have now been made; I welcome them because they mean that transport, and certainly rail projects, score much higher. We will of course ensure that that is rigorous, and that the preparation is transparent. I note my hon. Friend’s expertise in this area from his academic background and his business work. I am keen to work with him to ensure the business case works and is in the right form. He can take that assurance.

The hon. Member for Slough visited Winslow. I did so too, and I was actually brought up a few miles away. I am a supporter of this project because when I went to the further education college in Aylesbury, I used to go over that bridge every day, and there was nothing going on underneath it. Now, as the hon. Gentleman is aware, there is a station that will be ready to be opened shortly, and off the back of that we have the housing and the school. The secondary school in Winslow closed down. I was at secondary school in Buckingham, and all the pupils had to be bussed over. That no longer has to happen, and it is the railway that has allowed that to be built. Winslow is a good example of the fact that, if we build the infrastructure, the rest follows.

I am keen to work with the hon. Member for Slough, because it is clear that he supports East West Rail and wants it delivered. I support his support, as it were. He talked about the electrification miles that have been built, but I have to correct the record. In the past 13 years, while we have been in government, 1,200 miles of railway has been electrified. In the previous 13 years, when the Labour party was in power, the figure was a paltry 63 miles. I am sure the hon. Gentleman will not wish to give me any lessons about how to electrify lines, because we are doing that.

Huw Merriman Portrait Huw Merriman
- Hansard - - - Excerpts

I know the hon. Gentleman is going to tell me that he will do a lot more in the future, but the trouble is that we only have Labour’s record to judge him on, not his future deeds. Go on, have a go.

Tanmanjeet Singh Dhesi Portrait Mr Dhesi
- Hansard - - - Excerpts

I would like to rebut what the Minister just said. I referred to what has been electrified in the past year, which is a mere 2.2 km of rail line. The Minister is right to point to the Conservative-led Governments’ record in the past 13 years, but having been Chair of the Transport Committee, he will also be aware that the previous Labour Government’s main priority was to invest tens of billions of pounds in our rolling stock to get rid of the old, inefficient trains that we inherited from the previous Conservative Government after 18 years of grinding public transport to a halt. Having got the rolling stock back up to full speed, the last decade has been a lost decade for electrification, which is what other European Governments have done. That is why I said that the Minister and the Conservative Government have been failing on electrification.

Huw Merriman Portrait Huw Merriman
- Hansard - - - Excerpts

That was more than an intervention. The reality is—

Tanmanjeet Singh Dhesi Portrait Mr Dhesi
- Hansard - - - Excerpts

It was a reality check!

Huw Merriman Portrait Huw Merriman
- Hansard - - - Excerpts

I am impressed with that argument, actually, that rather than electrifying lines—I am a big supporter of that, and we want to and will do more, as we have done 1,200 miles whereas, as I pointed out, in the previous 13 years Labour had done 63—there was a priority focus on rolling stock. That really is pulling the other one. We have been doing both during that whole process. If the hon. Member has been on an Azuma train, he will know full well that they have been delivered under our—

Mark Hendrick Portrait Sir Mark Hendrick (in the Chair)
- Hansard - - - Excerpts

Order. Can we stick to the subject, please?

Huw Merriman Portrait Huw Merriman
- Hansard - - - Excerpts

Of course, Sir Mark. I am happy to do so, but the invention was so long that I thought you might give me the grace of replying to it fully. I think the point has been made.

Overall, we are committed to the project of East West Rail. The hon. Member for Cambridge set out the case that was recognised—

Mohammad Yasin Portrait Mohammad Yasin
- Hansard - - - Excerpts

Will the Minister give way?

Huw Merriman Portrait Huw Merriman
- Hansard - - - Excerpts

I will make a little more progress, then I will perhaps give way one final time.

My hon. Friend the Member for North East Bedfordshire mentioned the housing challenges in the area. I recognise that, because, having family and being brought up between Oxford and Cambridge, I see that every single time I go back. He is right to prod me on the figures. In my own constituency, we have an 85% area of outstanding natural beauty. I would like to see more development, so that we have the housing, infrastructure and resources where I am, and spread that load more equally.

I recognise the points raised by most hon. Members that the housing will potentially impact their constituencies. I appreciate that, but I will come back to the point made by the hon. Member for Cambridge. We must ensure that cities such as Oxford and Cambridge can compete not just in this country, but internationally. It is absolutely vital that the scientists, entrepreneurs and innovators there who are coming up with extraordinary cures, which will help people not just in this country but around the world, have the support to do that. At the moment, they do not have a workforce. The idea of this line is to deliver a workforce to Oxford and Cambridge, to use Milton Keynes and allow towns such as Winslow to grow further and get schools in place. In my view, it is a good example of rail delivering for the regional economy. I truly believe that it will do that but, as I say, I know the impacts and I understand them. I want to work with hon. Members across the piece on behalf of their constituents so that they feel more reassured, understand what is going on, get the detail and reassurance and, where needed, get compensation, and so that we make the project work for them as well. I will take one final intervention, then I will conclude.

Mohammad Yasin Portrait Mohammad Yasin
- Hansard - - - Excerpts

The Minister mentioned a statutory consultation earlier that will take place from January next year. My constituents think that it is a tick-box exercise; they think that the decision has already been made. If the Minister wants to prove my constituents wrong, will he commit today—I made this point in my speech as well—that if the majority of people taking part in the statutory consultation go against these plans, he will ensure that he puts the proposals on hold? Let him prove my constituents wrong, if he can.

Huw Merriman Portrait Huw Merriman
- Hansard - - - Excerpts

That is not a commitment I can give. As we know, those who tend to write back on consultations tend to be the most affected and are therefore the most troubled by the issue. That is not the way that we would run a consultation. We have of course set out a preferred line of route and the ambition that this railway can deliver, but I can give the hon. Member the assurance—I say this as a former Chair of a Select Committee—that consultations run in my Department under my name will be run properly. We will look at all the responses that come back and at where we can make improvements because residents have come up with really good ideas that will be a win for everyone. I expect to look at those closely and work with those suggestions. It will not be a tick-box exercise for as long as I am responsible for the project; I can give the hon. Member that assurance.

I will wrap up. As I stated, I encourage my hon. Friend the Member for North East Bedfordshire and his constituents to continue to use the opportunities provided through the East West Rail company’s community events and its forthcoming consultation to provide feedback on the plans. I will conclude by thanking you, Sir Mark, and all those who have spoken with passion and expertise. I give my commitment that the Department for Transport will work closely with all the MPs who are represented and have concerns. I hope to assure those who have the most striking concerns and deliver for those who believe, like me, that East West Rail can be a power for good in the region.

Mark Hendrick Portrait Sir Mark Hendrick (in the Chair)
- Hansard - - - Excerpts

I call Richard Fuller to wind up, cognisant of the fact that there is likely to be a vote at around 4 o’clock.