Draft Environmental Permitting (England and Wales) (Amendment) (No. 2) Regulations 2016

(Limited Text - Ministerial Extracts only)

Read Full debate
Tuesday 8th March 2016

(8 years, 8 months ago)

General Committees
Read Hansard Text
Rory Stewart Portrait The Parliamentary Under-Secretary of State for Environment, Food and Rural Affairs (Rory Stewart)
- Hansard - - - Excerpts

I beg to move,

That the committee has considered the draft Environmental Permitting (England and Wales) (Amendment) (No. 2) Regulations 2016.

The regulations are designed to simplify the permitting process and make more straightforward the way in which we deal with works in rivers. Previously, the process was governed by complicated legislation from the 1970s and 1990s that ensured that a bespoke permit requiring a detailed application and assessment was needed for anything that happened in relation to a river, whether that concerned bridges, culverts, outflow pipes or work on banks.

The new system is an attempt to move to a more straightforward procedure whereby in the highest-risk cases—around half of cases—a bespoke permit is still required, but for others there is a simplified process. For some excluded categories, there will be no need for anything at all. Simple, straightforward works, such as putting a ladder or piece of scaffolding in the river temporarily, will not require any form of permit.

The second type of procedure is an exempt procedure, for which all that is necessary is for someone to register the works.

Neil Parish Portrait Neil Parish (Tiverton and Honiton) (Con)
- Hansard - - - Excerpts

I am interested in the ideas that my hon. Friend the Minister is putting forward. Will the regulations make it easier or more difficult to get a permit if, for example, there was local management of a river and we wanted to do a little dredging here and there?

Rory Stewart Portrait Rory Stewart
- Hansard - - - Excerpts

Provided that the dredging work being undertaken was in the category for a registered exemption, all someone would have to do for works under 1.5 km is register that they were doing them and ensure that they had fulfilled the conditions of the exemption. They would then be able to proceed with the work. In the past, they would have had to make a bespoke application with a lot of detailed plans and drawings that would be considered on a case-by-case basis. We believe, though, that in low-risk cases of agricultural dredging that are not in areas of special scientific interest, it should be possible for people to fulfil a simple registration, follow the conditions and proceed. An example would be regular winter dredging.

There are essentially four different categories. The first, which I touched on briefly, is the excluded category, for which no permit at all is needed. For the second—the exempt category—people simply register online.

The third category is the standard rule permit, which requires people to seek permission—it is not just registration—and they have to follow standard conditions. For example, if someone is running an electric cable across the river, the conditions relate to putting it 1 metre or 1.5 metres under the river bed, starting around 8 metres from the edge of the river. There is, though, still a requirement for the agency—in this case the Environment Agency—to check the plans and drawings to ensure that the person has complied.

The final category is where the bespoke permits remain in place, but they are reduced to around half of cases.

Lord Mann Portrait John Mann (Bassetlaw) (Lab)
- Hansard - - - Excerpts

If one of my neighbours has a house adjoining the river, they potentially have a vested interest in any works that are done. What rights would they have to know about works being carried out and to object to the detail of how those works were done, in order to protect their own land and property?

Rory Stewart Portrait Rory Stewart
- Hansard - - - Excerpts

The hon. Gentleman asks a very good question. We have to differentiate three different questions: first, the nature of that person’s interest in that river; secondly, the nature of the work being undertaken; and, thirdly, the existing procedures to go through some form of objection.

I will take the categories in turn. To take the most simple case in the exempt category, for someone putting a ladder in the river that is removed at the end of the day, the answer to the neighbour is that that is an exempt activity, and the neighbour would have no opportunity to object.

For the second category, let us imagine that someone is running a more complicated utility across a river, such as an electric cable. If it was covered under one of the exempt categories, a registration would be submitted and there would be a possibility to examine that registration. If the activity registered did not comply with the standard conditions, such as if that cable had not been put 1 metre under the river bed or placed 8 metres from the edge of the river bank, there would be the possibility for the Environment Agency to intervene.

For the third category, which is more complicated work—not a simple wooden footbridge, but the insertion of a larger single-span bridge, perhaps with concrete piles—it would be necessary to go through a procedure and to understand the rules under which such plans would need to be submitted, and the Environment Agency would review.

Finally, if it was a very complex piece of work that would require a bespoke permit, a full case-by-case examination would have to take place.

We are simplifying the paperwork, and the benefit of that is that we move away from a complicated application for flood defence consent in which people were forced to fill in detailed plans and drawings, even for quite trivial works in the river. There were two problems with the complicated application. First, in certain cases, people were wasting a lot of time and energy, spending half an hour filling in the form and hours preparing their plans. The second probably more serious problem was that, in many cases for trivial works, people probably simply circumvented the law and did not fill in the documents in the first place, which was not to be encouraged.

We are moving to a situation where we will be much clearer that simple trivial works are exempt. If, on the other hand, people need to proceed, we have a much simpler form. People tick what they are doing, such as “repair of the floodbank”, and fill the form in. It takes about five minutes. For those simple types of work that will not have a significant impact either on the flow of the river or on floodwater moving around the side of the river, there should be no serious impact.

The second thing we are doing is that we are rationalising some of the legal anomalies in the environmental permitting regulations. For the 5% of cases where it was necessary in the past to apply for two separate permits—people had to fill two separate application forms and receive two different permits: one environmental permit and one flood permit—we are putting regulations in place that will allow people to have a single process with a single permit and a single application form. By doing so, we will ensure that the Environment Agency is focused on the most risky, most serious activity and that it does not waste its time looking at trivial things. It will therefore have a better quality of attention, which will be better for our environment and our flood risk. With that, I commend the regulations to the Committee.

--- Later in debate ---
Rory Stewart Portrait Rory Stewart
- Hansard - - - Excerpts

We have heard two serious interventions on different issues. The hon. Member for Stockton North focused on the issues of dredging, risk, resources and who is best placed to deal with these issues, while the hon. Member for Bassetlaw focused on banks and charging. I will take them in reverse order.

I am pleased that the hon. Member for Bassetlaw recognises the significant changes that will happen in terms of work on banks. That is a way of addressing some of the concerns raised by the hon. Member for Stockton North. The principle is one of looking at what “minor works” on banks mean—less than 10 metres, for example, would require only a registered exemption, while less than 20 metres would be under a standard rules permit. That is a big change from the old system, where a bespoke permit was needed for any work at all done on a bank.

I can reassure the hon. Member for Bassetlaw that the regulations are not introducing charges. There is, of course, a legal possibility for charges to be looked at, but they would be looked at under a separate instrument following a detailed consultation. I reassure him that we are not debating the question of charges today.

That brings me to the powerful speech made by the hon. Member for Stockton North. I will run through the various issues he raised. A lot of people have talked about dredging. Although we have exclusions and exemptions in relation to that, they have to follow very clear standard conditions. If those standard conditions are not met, that dredging is not legitimate. That relates to the question raised by the Chair of the Environment, Food and Rural Affairs Committee, my hon. Friend the Member for Tiverton and Honiton. We cannot dredge if, for example, we are dredging into an area with a site of special scientific interest, or a Ramsar site. This applies only to dealing with agricultural drainage ditches that are considered within the main river system. It would tend to apply, generally speaking, to low-lying areas. We are not talking about massive flood alleviation schemes. Our engineers believe that the requirement of limiting work to 1.5 km will deal with any serious issues around flooding.

Rebecca Pow Portrait Rebecca Pow (Taunton Deane) (Con)
- Hansard - - - Excerpts

Will the Minister comment on the proposals for the short areas that farmers, for example, might dredge? If they had been allowed to do that previously and to apply for these permits—I have talked to lots of farmers in Somerset about this issue—might it have helped to reduce the awful flooding that we saw in 2014-15?

Rory Stewart Portrait Rory Stewart
- Hansard - - - Excerpts

That is a very good question. I think the answer to my hon. Friend is that in an extreme weather event, such as the sort she saw in Somerset, the regular removal of silt from a 1.5 km-ditch is unlikely to have a significant impact on downstream flooding. What it would do in normal cases of winter flooding, is reduce the flooding of agricultural fields which would be good. So it is good for the general operation of farm business in normal winter flooding situations, but in an extreme weather event I am afraid that 1.5 km of silt removal is unlikely to tip the difference.

Seema Kennedy Portrait Seema Kennedy (South Ribble) (Con)
- Hansard - - - Excerpts

I welcome these proposals. As my hon. Friend the Minister knows, I also have many low-lying agricultural areas in my constituency that have suffered from flooding. Many of my farmers have asked for simplification about dredging and I wondered how the Department will communicate this simplification to landowners, so that they know about it and can save time in what they are doing.

Rory Stewart Portrait Rory Stewart
- Hansard - - - Excerpts

My hon. Friend asks a very good question. The answer is that we began the communication process through a highly publicised speech given by the Secretary of State at the Oxford farming conference, which got a lot of coverage in the agricultural press. There is increasing awareness now among the farming community of this future exclusion, but clearly we can do more. We will do our best to work with my hon. Friend, with the Chair of the Environment, Food and Rural Affairs Committee, and particularly with the trade press, to make sure that farmers are now aware of the new procedures. In my experience, farmers generally cotton on very quickly to these kinds of legislative changes, but I am happy to take up the challenge if they want.

I will move forward to address the questions put by the hon. Member for Stockton North. Regarding the question of the calculation of risk and who calculates it, essentially that process has been led by water engineers within the Environment Agency. Some of the exclusions and exemptions are genuinely very low risk indeed. If we look through the list of the exclusions, it was necessary in the past to obtain a bespoke permit, in theory even if someone was just putting a floodgate over their house. Ambiguities within the legal drafting meant that anything that could possibly affect the flow of water, such as someone not letting water into their front door, could have required a bespoke permit.

In the past, putting a sign into a river required an entire bespoke permit. Now, there is absolutely no engineering evidence whatsoever that sticking a small pole into a river will have a significant impact on flooding downstream. However, to reassure the hon. Gentleman, I will point out that the process is very much driven by a cautionary principle—people are being very risk-averse. We have made sure that we have excluded only the very lowest risk activities. Again, registered exemptions are very carefully controlled. In fact, we have had some complaints from people who would like to see us go much further.

The reason we have had to be quite careful is that the measure has to apply to all rivers across the country; it is not possible for us to come up with a single set of rules without being very cautious. For example, there is a standard exemption for scaffolding to extend across 10% of a river. People come back to us and say, “Well, that doesn’t make much sense. If my river is only eight miles wide, you are allowing me to put only 0.8 meters of scaffolding into the river.” The reason for that is that we have to make sure we are very, very cautious, which is why nearly half of these cases will still require bespoke permits. We have to deal with the fact that every river is different, every condition is different and the hydrology of these different river systems is very testing. However, in straightforward cases—a noticeboard or a ladder going into a river, or a simple piece of work on banks, as mentioned by the hon. Member for Bassetlaw—we have taken the view that a calculated risk makes sense.

Finally, on the question of who is best placed to make such decisions, whether on IDBs or the action of local councils, the draft regulations apply primarily to main rivers, which is to say the rivers and streams that we believe have a significant impact on a large degree of flooding. Most of the local authority responsibility will relate to flood risk in general and include a lot of rivers that are not classified under the regulations as a “main river”.

In terms of the resources to be brought to bear, we believe that rather than imposing more costs on individuals, the Environment Agency should be saved about half a million pounds a year—a significant saving—and businesses about £14 million over 10 years. Those financial savings are only the beginning, from my point of view; the real saving is getting rid of the forms. Nothing is more eroding to trust in Government in the general sense of energy and common sense in action than having to fill out forms to put a ladder or a simple signpost into a river.

Alex Cunningham Portrait Alex Cunningham
- Hansard - - - Excerpts

I thank the Minister for his explanation. None of us doubts the wise measures in place as far as the smaller things are concerned, but I am concerned about monitoring some of the more extensive work that will not require the same level of permit as in the past.

Rory Stewart Portrait Rory Stewart
- Hansard - - - Excerpts

In order to deal with the serious stuff, which is to do with major works on bridges, culverts, banks, utility crossings and outflows—water coming in—a full, bespoke Environment Agency permitting system is in place and covers nearly 50% of the applications. Officers in such cases will require full plans, drawings and impact assessments, will have to inspect the individual rivers and will look in detail at the proposed works case by case.

Alex Cunningham Portrait Alex Cunningham
- Hansard - - - Excerpts

I am sorry—I think I just invited the Minister to repeat what he said earlier—but I am talking about what will not require a permit under the regulations. He started to talk about the more extensive work, but he has addressed that; I am asking about the marginal stuff, where there will be changes. For example, 1.5 km of river is a fairly extensive piece of river, so I am interested in what monitoring of that will be like in future, so that we know the new regulations are working.

Rory Stewart Portrait Rory Stewart
- Hansard - - - Excerpts

Dredging and the 1.5 km are perhaps a misleading example. That is about maintenance of silt levels in existing agricultural drainage ditches in areas that are not of environmental importance. The rest of the things that are excluded are, genuinely, very minor works indeed. We are literally getting down to the level of a ladder or a sign board being put daily into the river; a service crossing with an existing structure, or, in other words, someone putting an electric wire through a pipe that already exists in a bridge; a 48-hour temporary trial pit; an investigation borehole; or clearance of sediment traps. For anything above that, such as exposed gravel removal, a large outfall or headwall, or a large habitat structure, the full regulatory system remains in place. I hope that reassures the hon. Gentleman and the rest of the Committee. I commend the draft regulations to the Committee.

Question put and agreed to.