High Speed 2 Line: Construction

(asked on 7th December 2023) - View Source

Question to the Department for Transport:

To ask His Majesty's Government, following the cancellation of the Northern Phase of HS2, whether any damage caused to the countryside and environment by the workings of contractors will be remedied at the expense of the HS2 budget.


Answered by
Lord Davies of Gower Portrait
Lord Davies of Gower
Shadow Minister (Home Office)
This question was answered on 15th December 2023

As part of ensuring an orderly and respectful close-down of the northern phase of HS2, HS2 Ltd will be reviewing those works that have already taken place and considering the best course of action to take on a case-by-case basis. This may mean restoring some sites to their former condition; it may also mean leaving some early environmental enhancement works in place. No sites will be left incomplete, and all close-down activities will be funded from the HS2 budget.