East Coast Railway Line

(asked on 5th June 2014) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government, further to the Written Answer by Baroness Kramer on 13 May (WA 492), what is the annual charge used to calculate the net present value of £2.7 billion for the contract with Agility Trains East covering the provision of Intercity Express trains for the East Coast Main Line; and how many diagrammed trains and diagrammed vehicles are to be provided under the contract.


Answered by
Baroness Kramer Portrait
Baroness Kramer
Liberal Democrat Lords Spokesperson (Treasury and Economy)
This question was answered on 19th June 2014

The net present value of the East Coast Main Line fleet is £2.7bn in 2009 prices. This is for a fleet of 414 diagrammed vehicles over 54 diagrammed trains. The total Set Availability Payment for the full East Coast fleet in 1 April 2020 - 31 March 2021 (the first year of full fleet operation) is £324.6m in nominal 2020 prices.