Reservoirs: Construction

(asked on 13th May 2025) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask His Majesty's Government, further to the Written Answer by Baroness Hayman of Ullock on 12 May (HL7055), which sites are being considered for the potential ten new reservoirs; and on what timescale they intend that the new reservoirs should become operational.


Answered by
Baroness Hayman of Ullock Portrait
Baroness Hayman of Ullock
Parliamentary Under-Secretary (Department for Environment, Food and Rural Affairs)
This question was answered on 21st May 2025

The following new reservoir sites (with a capacity above 10 million litres per day) have been identified in water company’s latest statutory water resources management plans, with their capacity and expected completion date provided in the table below.

Reservoirs

Water company

Daily supply (Ml/d)

Start year

Broad Oak

South East Water

12.6

2033

Cheddar 2

South West Water

13

2035

Fens

Anglian Water, Cambridge Water

87

2036

Mendips Quarry

South West Water

46

2042

River Adur offline reservoir

Southern Water

19.5

2045

South East Strategic Resource Option

Thames Water, Affinity Water, Southern Water

293

2039

South Lincs

Anglian Water

166.5

2040

North Suffolk

Essex and Suffolk Water

19.9

2040

West Midlands

Severn Trent Water

32.5

2040


In addition to the nine sites above, work is already underway on Portsmouth Water’s Havant Thicket reservoir, as set out in the company’s WRMP19. This will supply an expected 21 Ml/d, with a latest forecast completion date of 2031-32.

The one reservoir enlargement is set out below.

Reservoir enlargement

Water company

Daily supply (Ml/d)

Start year

Tittesworth

Severn Trent Water

14

2049