High Speed 2 Railway Line

(asked on 16th March 2016) - View Source

Question to the Department for Transport:

To ask Her Majesty’s Government what is their latest estimate of (1) the number of HS2 trains of each size required for HS2 Phase 1 and HS2 Phase 2, and (2) the total cost (a) of each type of train, and (b) for each phase.


Answered by
 Portrait
Lord Ahmad of Wimbledon
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 30th March 2016

The Functional Response annexed to the Development Agreement outlines what HS2 Ltd will deliver to satisfy the Sponsor’s Requirements, including capacity requirements for both phases of the new railway. HS2 Ltd are in the process of completing their Rolling Stock Strategy which will contain greater detail on the fleet sizes expected to be procured.

As part of the Spending Round announced in November 2015, the rolling stock funding envelope has been integrated with the relevant Phase specific infrastructure funding envelope as shown below.

Phase One

27.2

Phase Two

28.5

Programme Total

55.7

Note. The above table shows information in £Billion at 2015 prices.