Old Oak Common Station: Construction

(asked on 10th March 2022) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what is the latest budget estimate for the Old Oak Common station on the Great Western Main Line; how many platform faces are included; and whether this is included in the overall HS2 budget as set out in the integrated Rail Plan.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 21st March 2022

Old Oak Common will contain 14 platforms: 6 subterranean High Speed platforms and 8 conventional rail platforms.

Within the Target Cost for Phase One - which is included in the Integrated Rail Plan (IRP) - the budget allocated by HS2 Ltd for Old Oak Common station, including contingency for risk, is £1.67bn (2019 prices). A more detailed breakdown of costs cannot be provided as this information is commercially sensitive.