Question to the Department for Transport:

To ask Her Majesty’s Government for how many months roadworks have been underway on the M3 motorway between the Fleet Services and the M25; for how many months those roadworks are expected to continue; what was the initial cost estimate for those works; and what is the current estimated cost.


Answered by
 Portrait
Lord Ahmad of Wimbledon
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 26th April 2017

The roadworks underway on the M3 between junctions 2 (the M25) and 4a near Fleet services) consist of two combined schemes (a Smart Motorway scheme and a maintenance scheme). These have been underway for 26 months, and are currently due to finish construction in two months in June 2017. The cost estimate approved for these works was £256 million. The current estimated outturn cost of the scheme is also £256 million.