Question to the Department for Transport:
To ask Her Majesty’s Government for how many months roadworks have been underway on the M3 motorway between the Fleet Services and the M25; for how many months those roadworks are expected to continue; what was the initial cost estimate for those works; and what is the current estimated cost.
The roadworks underway on the M3 between junctions 2 (the M25) and 4a near Fleet services) consist of two combined schemes (a Smart Motorway scheme and a maintenance scheme). These have been underway for 26 months, and are currently due to finish construction in two months in June 2017. The cost estimate approved for these works was £256 million. The current estimated outturn cost of the scheme is also £256 million.