Question to the Ministry of Justice:
To ask His Majesty's Government what plans, if any, they have to expand HMP Highpoint.
The Ministry of Justice is delivering an additional c.700 places at HMP Highpoint through the construction of three four-storey houseblocks and supporting ancillaries. Construction work started at HMP Highpoint in November 2024, with prisoners expected in the new accommodation by the end of 2027.
This expansion programme is being delivered as part of the 20,000 Prison Place Programmes. In the 10-Year Prison Capacity Strategy, published in December 2024, the Lord Chancellor committed to delivering the remaining 14,000 places of the programmes, with an aim to complete delivery by 2031.