Question to the Department for Transport:
To ask His Majesty's Government, further to the Written Statement by the Secretary of State for Transport on 9 March (HCWS625), what (1) development, (2) design, and (3) construction, activities will be delayed for two years on HS2 (a) Phase 2A, (b) Phase 2B, and (c) Phase 1 Old Oak Common to Euston; and how much money will be saved as a result of those delays.
The Secretary of State for Transport made a written statement to Parliament on 9 March 2023, setting out plans for rephasing some elements of the HS2 scheme. The Department for Transport is continuing to work through the implications of the funding settlement with HS2 Ltd. The Department for Transport publishes six-monthly parliamentary reports on HS2 and will provide updates in due course.