Question to the Department for Transport:
To ask His Majesty's Government what is the percentage completion of construction in respect of HS2 Phase 1 of the Colne Valley Viaduct.
It is not possible to give a percentage completion of the Colne Valley Viaduct as it has structural components that are constructed progressively, with different structures at various levels of completion. To illustrate progress, all abutments are complete, 206 precast segments have been erected, and 26 piers completed.