Question to the Department for Environment, Food and Rural Affairs:
To ask His Majesty's Government what estimate they have made of the total cost of building and completing each of the Border Control Posts in Northern Ireland; and what is the estimated date of completion of each one.
In line with the commitments we have made under the Windsor Framework, SPS inspection facilities are under construction in Northern Ireland at the ports of Belfast, Larne, Foyle and Warrenpoint. Preparations are well underway, and they will be operationally ready by July 2025.
The Government has committed to a maximum funding envelope of £192.3 million. Of this envelope, Defra has spent £70.7 million up to 28 February 2025, the latest data currently available.