Question to the Department for Transport:
To ask Her Majesty's Government what methodology was used by HS2 Ltd to estimate the costs of the HS2 Phase One line of route between London and the West Midlands.
HS2 Ltd has used a range of methodologies to estimate the cost of Phase 1 including New Rules of Measurement (NRM), Rail Method of Measurement (RMM), and Civil Engineering Standard Method of Measurement (CESMM). The estimates are tested through benchmarking techniques and ultimately validated through the contracted prices secured with suppliers.