To ask Her Majesty's Government what conditions the Environment Agency has imposed on HS2 in connection with the construction of the Chiltern Tunnel; and whether they will publish copies of all documents issued by the Environment Agency in connection with their consent to construction of the Chiltern tunnel.


This question was answered on 25th May 2021

The conditions imposed on the construction of the Chiltern Tunnel are within the relevant consents that have been issued by the Environment Agency. The consent for the construction of the tunnel (HS2/P10191) will be deposited in the Library of the House. The related consents for water discharge (EPR-QB3092NR) and waste treatment (FB3709KP) at the Chilterns Tunnel South Portal are held on the public register.