Question to the Department for Transport:
To ask His Majesty's Government what funding they are making available for the development of Northern Powerhouse Rail between now and April 2025; and how many staff are currently engaged on this project.
The Northern Powerhouse Rail accounting officer assessment summary published on 30 July set out that £54m has been budgeted for development work on the scheme in 2024/25. Expenditure of a further £34m is anticipated on the High Speed Rail (Crewe – Manchester) Bill, excluding purchase costs for land and property.
There are around 40 full-time equivalent officials in the Department for Transport working on Northern Powerhouse Rail. This is reflective of the current stage of development and proposals. The Department for Transport is supported in its development of Northern Powerhouse Rail by Network Rail, HS2 Ltd and Transport for the North.