Question to the Department for Transport:
To ask His Majesty's Government, further to the Written Answer by Lord Hendy of Richmond Hill on 18 February (HL4719), whether they were (1) part of the Manchester Task Force, or (2) consulted by them, with regards to the withdrawal of the direct Sheffield to Manchester Airport train; and if so, whether they supported the decision.
The Manchester Task Force (MTF) began meeting in February 2020, made up of Department for Transport, Network Rail, train operators, Rail North Partnership, Transport for the North and Transport for Greater Manchester. Through gathering evidence, developing options and publicly consulting, the task force identified a range of short and long-term actions to improve the performance of the railway in Manchester/across the North and support future growth in passengers.
The task force identified the Sheffield-Manchester Airport service, which reversed at Manchester Piccadilly, consuming two train paths in each direction, as one of the worst performing, with a significant impact on delays across the network.
The new timetable developed by MTF has delivered improvements in reliability of around 30 per cent, and the task force concept is now being used to resolve issues on the East Coast main line. As new infrastructure is realised and longer trains allow for a greater capacity with less congestion, we will look at services that could be reintroduced, possibly including direct services from Sheffield to the Airport, although there could be other towns and cities making a case for their pre-2022 direct connections to be restored as well.