National Holocaust Memorial Centre and Learning Service

(asked on 21st January 2025) - View Source

Question to the Ministry of Housing, Communities and Local Government:

To ask His Majesty's Government, further to the remarks by the Parliamentary Under-Secretary of State for Levelling Up, Housing and Communities on 22 May 2024 (HC Deb cols 975–6) that £18 million had already been spent on the planned UK Holocaust Memorial and Learning Centre, how much they have spent since that date and what the additional spending relates to.


Answered by
Lord Khan of Burnley Portrait
Lord Khan of Burnley
Parliamentary Under-Secretary (Housing, Communities and Local Government)
This question was answered on 13th February 2025

From 1 April 2023 to 22 January 2025 £2.71 million has been spent on project costs, including work on the Holocaust Memorial Bill, preparations for redetermination of the planning application and preparation for the commencement of construction. £1.66 million of that money has been spent since 22 May 2024.