To ask His Majesty's Government what are the expected opening dates for passengers of (1) the Euston HS2 station, (2) the Old Oak Common HS2 station, and (3) the Old Oak Common mainline station.
It has been the plan for several years to open Euston after the Old Oak Common to Curzon Street section. A new delivery-into-service date range for Euston will be confirmed once we have further progressed work on the affordability of the station design
Old Oak Common is estimated to be operational between 2029-2033. The large Christmas possessions that enable services to run on the new track layout, through Old Oak Common station, are currently being replanned and further information will be available from Spring 2025.