High Speed 2 Railway Line: Costs

(asked on 22nd April 2020) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government, further to Full business case High Speed 2 Phase One, published on 15 April, what is the total amount of the ‘sunk costs’; what costs incurred before December 2019 were not included in the economic appraisal; what would the benefit-cost ratio figures be if those costs had been included; whether the writing off of development costs up to the time of Notice to Proceed is in compliance with the HM Treasury's Green Book; what other Government-funded projects have had the development costs written off; and whether any such costs were written off in order to improve the benefit-cost ratio figures.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 6th May 2020

The spend to date on HS2 up to the end of 2019 was £7.5bn (2015Q1 prices, excluding VAT). However not all of this is treated as sunk costs in the economic case as the land and property costs could be recoverable were HS2 not to go ahead.

what would the benefit-cost ratio figures be if those costs had been included;

The benefit cost ratio figures including sunk costs are as follows:

Full Network

Statement of Intent

Parliamentary Powers

BCR without WEIs

1.1

0.8

0.8

BCR with WEIs

1.3

1.0

1.0

whether the writing off of development costs up to the time of Notice to Proceed is in compliance with the HM Treasury's Green Book;

The appraisal of HS2 has been undertaken in compliance with HM Treasury’s Green Book. The Green Book states that “what matters are costs and benefits affected by decisions still to be made.”

what other Government-funded projects have had the development costs written off; and whether any such costs were written off in order to improve the benefit-cost ratio figures.

Costs have not been written off in the approval of HS2. HS2 Ltd’s delegated Funding Envelope (the “Target Cost”) for Phase One is £40bn (2019 prices). This Target Cost includes the costs already spent on the project.