Mobile Phones: Northern Ireland

(asked on 21st October 2015) - View Source

Question to the Department for Digital, Culture, Media & Sport:

To ask Her Majesty’s Government when and where the Mobile Infrastructure Project will be rolled out in Northern Ireland.


Answered by
Baroness Neville-Rolfe Portrait
Baroness Neville-Rolfe
Minister of State (Cabinet Office)
This question was answered on 3rd November 2015

The Mobile Infrastructure Project is being rolled out in Northern Ireland up to the end of March 2016.


There are currently 7 masts in build phase. These are located in:

• Derry and Strabane District

• Fermanagh and Omagh (2 sites)

• Lisburn and Castlereagh

• Mid Ulster (3 sites)


Planning permission was received for 4 sites. These sites are located in:

• Mid Ulster (3 sites)

• Newry, Mourne and Down


Planning applications were submitted but decisions awaiting for 5 other sites. These are located in:

• Armagh, Banbridge and Craigavon

• Derry and Strabane District

• Fermanagh and Omagh (2 sites)

• Mid Ulster