To ask His Majesty's Government what is the (1) original, and (2) current, estimated completion date of the update to Oxford station, including the new western entrance and platform five.


Answered by
Lord Hendy of Richmond Hill Portrait
Lord Hendy of Richmond Hill
Minister of State (Department for Transport)
This question was answered on 16th September 2026

Botley Road was originally expected to open in October 24 and is now expected to open in September 2026. The remaining works in the Oxford station project are expected to be completed by mid-2029 to support the planned introduction of East West Rail services.