Question to the Department for Transport:
To ask His Majesty's Government what area of the 21.16 hectare Bow Tie Field at Stonehenge would have to be compulsorily acquired for construction of a new dual carriageway, eastern tunnel portals and tunnels as a part of National Highways’ proposed A303 Amesbury to Berwick Down scheme.
The area within Bow Tie Field identified as being required for compulsory acquisition for construction of a new dual carriageway, eastern tunnel portals and tunnels are as follows:
Approximately 4.54 hectares of permanent acquisition,
Approximately 6.65 hectares of permanent subsoil (subterranean) rights for the tunnel.