Crossrail Line

(asked on 12th July 2021) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what is the expected final (1) completion date, and (2) cost, of Crossrail; and what lessons are there, if any, for the HS2 project.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 23rd July 2021

Crossrail comes under the remit of the Mayor of London.

In August 2020, Crossrail Limited announced that the central section of the railway will open in the first half of 2022. Following the opening of the central section, full services across the Elizabeth line from Reading and Heathrow in the west and between Abbey Wood and Shenfield in the east, will be introduced.

Crossrail Ltd.’s overall cost forecast of completing the programme is up to £18.9 billion. This includes Network Rail On-Network Costs for the surface works but excludes the new trains and depot.