High Speed 2 Railway Line: Colne Valley

(asked on 25th February 2020) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask Her Majesty's Government what reasons the Environment Agency gave for allowing HS2 Ltd to drill at the Harvil Road site in the Colne Valley.


This question was answered on 5th March 2020

The Environment Agency (EA) has given permission to High Speed Two (HS2) Ltd to carry out drilling activities at the Harvil Road site under Schedule 33 of the High Speed Rail (London – West Midlands) Act 2017.

The EA reviewed the risks to groundwater quality and quantity by the HS2 Ltd construction activities at the Harvil Road site in the Colne Valley and did not identify any reasons to prohibit drilling activities at the site.