To ask Her Majesty's Government what plans they have to make a decision on (1) whether to grant Sizewell C a Development Consent Order, or (2) any commitment of public investment in Sizewell C, before the appointment of a new Prime Minister; and what assessment they have made of the conformity of any such decisions with the Prime Minister’s statement to Cabinet on 6 July that major fiscal decisions should be left for the next Prime Minister.


Answered by
Lord Callanan Portrait
Lord Callanan
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 26th July 2022

The Secretary of State granted development consent for the Sizewell C Nuclear Power Station on July 20th 2022, after thorough consideration of all relevant information.

Commercial negotiations on the project are strictly separate from consideration of the application for development consent. To date these negotiations have been constructive, but are ongoing and no decisions have been made.