Sizewell C Power Station

(asked on 13th July 2022) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask Her Majesty's Government which minister from the Department for Business, Energy and Industrial Strategy will be making the decision as to whether Sizewell C will be granted a Development Consent Order.


Answered by
Lord Callanan Portrait
Lord Callanan
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 26th July 2022

The decision on the application for development consent for Sizewell C Nuclear Power Station was announced on 20 July 2022. The then Parliamentary Under Secretary of State Paul Scully took the decision on behalf of the Secretary of State who had confirmed that his delegation of the decision-making powers to Minister Scully in respect of the Sizewell C application should continue, notwithstanding Minister Scully’s move to the Department for Levelling Up, Housing and Communities.