Bridges: Somerset

(asked on 24th March 2026) - View Source

Question to the Department for Transport:

To ask His Majesty's Government, further to the Written Answer by Lord Hendy of Richmond Hill on 13 February (HL14187), whether National Highways produced a completion report for the infilling work on Ridge Road Bridge; and if so, whether that report recorded the south span of Ridge Road Bridge as (1) infilled, or (2) not infilled.


Answered by
Lord Hendy of Richmond Hill Portrait
Lord Hendy of Richmond Hill
Minister of State (Department for Transport)
This question was answered on 13th April 2026

In line with current practice, the supervisor (contracted by National Highways) reported progress weekly and therefore no completion report was required.

National Highways has confirmed that the south span was ultimately found not to be fully infilled.