High Speed 2 Railway Line

(asked on 28th March 2019) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what are the latest estimated costs of the HS2 project; and when the line is expected to open.


Answered by
Baroness Sugg Portrait
Baroness Sugg
This question was answered on 11th April 2019

The 2015 Spending Review confirmed a funding envelope for the whole of HS2 of £55.7bn in 2015 prices.

HS2 Ltd has been set Delivery-In-Service targets by Government under its Development Agreement, which are to deliver initial Phase One services from 2026 and the whole HS2 network by 2033.

HS2 Ltd is currently working with their contracted suppliers to update and agree the latest cost and schedule positions for Phase One. Once completed we will make these details public as part of the Phase One Full Business Case, which is due for publication later in 2019.