High Speed 2 Railway Line: Wendover

(asked on 23rd February 2021) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government, further to the Written Answer by Baroness Vere of Norbiton on 9 February (HL12883), on what (1) dates, and (2) times, did EKFB contractors meet with (a) HS2 Ltd, and (b) officials at the Department for Transport, to provide advice on the scrutiny of the Wendover Mined Tunnel, as such scrutiny has developed.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 2nd March 2021

Design contractors working on behalf of EK (as it was at the time) were present at one meeting between officials from the Department for Transport and HS2 Ltd to discuss the Wendover Mined Tunnel proposal. The meeting took place on 1 April 2019 at 3pm.