Question to the Department for Transport:
To ask His Majesty's Government, further to the Written Answer by Lord Hendy of Richmond Hill on 28 July 2025 (HL9776), what recent progress they have made towards ensuring that every platform has level boarding at the new Old Oak Common station.
Old Oak Common station will provide full street to platform step-free access, with HS2 platforms designed to offer full level boarding. Platforms serving the Elizabeth Line and conventional rail services have been designed to accommodate different kinds of rolling stock that have different boarding heights. Work to establish the feasibility and safety of deviating from standard 915mm platform heights on the relief line platforms (platforms 5-8, which will predominantly serve the Elizabeth Line) is continuing. Completed assessments to enable a final decision on this issue are expected by Spring 2026, with an announcement expected by the end of the year.