Question to the Department for Transport:
To ask His Majesty's Government what work they are undertaking towards the electrification of railways lines, in particular the Midland Main Line, and what is the timescale for that work.
The Midland Main Line (MML) is now electrified as far as Wigston, south of Leicester, which has enabled the phased introduction of East Midland Railway’s new bi-mode intercity trains to begin. As part of Spending Review 2025, however, the decision was taken to pause electrification of the remainder of the route to Nottingham and Sheffield via Derby.
Continued electrification remains part of this government’s approach to decarbonising our railways and this includes electrification of the MML. Although it is not currently funded within this Spending Review period, further electrification of the MML will be kept under active review and consideration, as part of our longer-term pipeline of proposed rail investment schemes.