To ask Her Majesty's Government how much they have spent on the purchase of land and property in connection with (1) HS2 Phase 1, and (2) HS2 Phase 2A.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 5th January 2021

At November 2020, some £3.642bn has been spent or committed on the three phases of the HS2 property programme. The breakdown is: Phase One - £3.314bn; Phase 2a - £100m; and, Phase 2b - £228m.