High Speed 2 Line: Construction

(asked on 12th December 2023) - View Source

Question to the Department for Transport:

To ask His Majesty's Government, further to the Written Answer by Lord Davies of Gower on 6 December (HL701), whether they will now answer the question put; namely, how much money has been spent to date on the Crewe leg (Phase 2a) of HS2.


Answered by
Lord Davies of Gower Portrait
Lord Davies of Gower
Shadow Secretary of State for Wales
This question was answered on 20th December 2023

As noted in the Parliamentary Report published in November 2023, to date £1bn (2019 prices) has been spent on the Phase 2a leg of HS2.