High Speed 2 Line: Land

(asked on 16th October 2023) - View Source

Question to the Department for Transport:

To ask His Majesty's Government, further to the announced cancellation of phase 2 of HS2, how much has been spent on the purchase of land for phase 2 of HS2 that is no longer necessary.


This question was answered on 26th October 2023

As of September 2023, £208m has been spent on land and property on Phase 2a and £356m on Phase 2b. Any property that is no longer required will be sold and a programme is being developed to do this.

Reticulating Splines