Question to the Department of Health and Social Care:
To ask the Secretary of State for Health and Social Care, what the (a) business case status and (b) RIBA stages are for the delivery of work on St Mary's Hospital as part of the New Hospitals Programme.
The standard process for confirming the total funding amount for major infrastructure projects involves the review and approval of a Full Business Case. All trusts in the programme have previously received indicative funding allocations to support planning, however these are commercially sensitive.
Up to the end of 2023/24 the total amount received by the Imperial College Healthcare NHS Trust in funding for their new hospital schemes is £13 million. The trust has two schemes in the New Hospital Programme for the Charing Cross Hospital and Hammersmith Hospital, as well as the scheme for St Mary’s Hospital. Up to the end of 2023/24, the funding allocated to the trust was not separated by the individual schemes.
The breakdown of how much the trust received for their new hospital scheme is published annually as part of the Department’s Annual Reports and Accounts, with Public Dividend Capital to individual Trusts included in the Financial Assistance Report under section 40 of the National Health Service Act 2006. The 2022/23 report is available at the following link:
https://www.gov.uk/government/publications/dhsc-annual-report-and-accounts-2022-to-2023
The trust is currently developing their Strategic Outline Case for the St Mary’s Hospital scheme and are at Royal Institute of British Architects Stage 1.