Question to the Department for Transport:
To ask the Secretary of State for Transport, what steps her Department is taking to ensure that there is adequate monitoring and oversight of the construction of HS2.
The Department for Transport monitors the construction of HS2 through formal mechanisms such as the HS2 Development Agreement, and a number of supporting forums which assess whether HS2 is being delivered to budget and schedule, and in accordance with the commitments which accompany both HS2 Acts.
The Department also deploys a team of independent Construction Inspectors to provide independent scrutiny of construction, as well as its impact on communities and residents.