Question to the Ministry of Housing, Communities and Local Government:
To ask the Secretary of State for Housing, Communities and Local Government, how many applications have waited longer than the 12-week timeframe that the Building Safety Regulator says it will take to complete its process in the last 12 months.
The Building Safety Regulator (BSR) has reported that 930 Gateway 2 applications decided in the last 12 months (between 24 October 2024 and 23 October 2025) took longer than 12 weeks to reach a decision.
The BSR is already making operational and policy changes to speed up decision making, particularly on building control approval, including through the introduction of an Innovation Unit and batching process. Early signs are positive with all applications in the Innovation Unit so far on track to exceed or meet the 12-week SLA target.