National Grid: Hinchingbrooke Hospital

(asked on 15th October 2025) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the potential merits of receiving approval from NESO for additional grid connection for the final phase of Hinchingbrooke Hospital’s rebuild.


Answered by
Michael Shanks Portrait
Michael Shanks
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 20th October 2025

Details of the requirements for individual connections to the electricity network are held in private connection contracts between the relevant parties.

Faster grid connections are crucial to the Government's clean energy superpower and growth missions. We announced plans in the Industrial Strategy on a series of measures to accelerate connections for strategically important demand projects.