To ask the Secretary of State for Defence, when the Army's headquarters in the North West at Weeton Barracks will be (a) completed and (b) operational.
I refer my hon. Friend to the answers I gave him on 14 October 2020, to Questions 100945, 100946 and 100947 where I said that, on current plans, HQ North West is scheduled to be re-located from Fulwood Barracks, Preston to Weeton Barracks in the summer of 2025.
However, my hon. Friend will be aware that the Army is working to implement the outcomes of the Integrated Review, including designing a force that is fit to face future threats. The Secretary of State for Defence will be making an announcement in due course which will provide more detail, including how any changes required as part of this transformation may affect current planned relocations.