Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, what estimate he has made of the potential contribution of the Norwich to Tilbury Great Grid upgrade to his target for low carbon generation of electricity by 2030; and when he expects this infrastructure will be operational.
National Grid have now submitted their Development Consent Order application to the Planning Inspectorate for consideration.
The Government does not comment on the merits of live planning applications, which, subject to the Planning Inspectorate’s decision to accept the application for examination, will be subject to rigorous, independent assessment and advice by the Examining Authority – to inform the Secretary of State’s final decision.
The project currently has an earliest in-service date 2031, and NESO’s independent advice on 2030 Clean Power demonstrates that failing to bring this forward to 2030 will reduce clean power on the GB grid by 1% and could increase constraint costs by £2.8bn p.a.