Railways: Waste Disposal

(asked on 3rd July 2020) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, which railway routes on the England and Wales rail network have temporary non-compliance status from Network Rail and allow the practice of dumping human waste and effluent on railway tracks.


Answered by
Chris Heaton-Harris Portrait
Chris Heaton-Harris
Secretary of State for Northern Ireland
This question was answered on 8th July 2020

Non-compliance status is granted to operators and not routes.

The following franchised train operators have applied for, and been granted, temporary non-compliance status: Chiltern, CrossCountry, East Midlands Railway, Great Western Railway, Greater Anglia, Northern, West Midlands Trains and Transport for Wales.

Other operators, such as charter and heritage, for which the Department is not responsible for have also been issued with non-compliance status by Network Rail.