Hinkley Point C Power Station

(asked on 23rd May 2022) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, what the revised estimated dates are for the commissioning of Hinkley Point C (a) reactor one and (b) reactor two; and whether there is any estimated additional programme risk on these dates.


Answered by
Greg Hands Portrait
Greg Hands
Minister of State (Department for Business and Trade)
This question was answered on 26th May 2022

EDF updated the forecast cost and schedule for Hinkley Point C on 19 May 2022. The forecast shows a Unit 1 Commercial Operation Date (COD) of June 2027 (12 months later than the current baseline schedule). Unit 2 is forecast to start 12 months after Unit 1. EDF estimate the risk of COD delay to both Units 1 and 2 is 15 months.