Flood Control: Ribble Valley

(asked on 13th March 2017) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask the Secretary of State for Environment, Food and Rural Affairs, how much her Department estimates will be spent on flood prevention in Ribble Valley constituency over the next five years.


Answered by
Thérèse Coffey Portrait
Thérèse Coffey
This question was answered on 16th March 2017

The Government plans to invest £642,338 in the Ribble Valley constituency to deliver the Whalley and Billington Surface Water Improvement Scheme over the next five years. The table below summarises planned Government investment for each of the five years.

2016/17

0

2017/18

0

2018/19

£30,000

2019/20

£83,780

2020/21

£528,558

These figures represent all funding that the Environment Agency currently estimates is allocated to the Ribble Valley constituency.